Consider the number of workers working on a project and the time taken by them to complete the work. We observe that the time taken to complete the work reduces if we increase the number of workers and the decrease in the number of workers lead to increase in the time of completion. Thus, the number of workers working on a project and the time taken to complete it are in inverse variation.
According to question
the time taken to complete the work reduces if we increase the number of workers and the decrease in the number of workers lead to increase in the time of completion.
Let us understand it with an example,
There is x apple and it is to be eaten by 5 people, then the time required to eat the apple will be, x5.
Now, if we increase the number of people to eat the apple from 5 to 10, then the time required to eat x apple will be, x10.
As we can see that, if we increase the number of people(n) the time taken(t) to complete a work will be reduced.
∴n∝1t.
Hence, we can say that, the number of workers working on a project and the time taken to complete it are in inverse variation.
Topper's Solved these Questions
Similar Questions
The number of workers and the time to complete a job is a case of direct proportion.
View SolutionTime taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?
View Solution
Knowledge Check
When the time taken to complete a given amount of work increases, then,
Apower increasesBpower decreasesCenergy increasesDenergy decreasesA Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
Aa. 10%Bb. 1427%Cc. 20%Dd. can't be determinedA Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
A10%B1427%C20%Dcan’t be determined
The number of workers in the employment · guarantee scheme increased by 15 which resulted into an increase of 20%. What was the initial number of workers ?
View SolutionThe following table shows classification of number of workers and the number of hours they work in a software company. Find the median of the number of hours they work.
View SolutionA takes 5 hours more time than that taken by B to complete a work. If working together they can complete a work in 6 hours, then the number of hours that takes to complete the work individually is
View SolutionIf 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.
View Solution20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per day, what is the time required to complete the work?
View Solution