Consider the number of workers working on a project and the time taken by them to complete the work. We observe that the time taken to complete the work reduces if we increase the number of workers and the decrease in the number of workers lead to increase in the time of completion. Thus, the number of workers working on a project and the time taken to complete it are in inverse variation.

Text Solution
Verified by Experts

According to question
the time taken to complete the work reduces if we increase the number of workers and the decrease in the number of workers lead to increase in the time of completion.
Let us understand it with an example,
There is x apple and it is to be eaten by 5 people, then the time required to eat the apple will be, x5.
Now, if we increase the number of people to eat the apple from 5 to 10, then the time required to eat x apple will be, x10.
As we can see that, if we increase the number of people(n) the time taken(t) to complete a work will be reduced.
n1t.
Hence, we can say that, the number of workers working on a project and the time taken to complete it are in inverse variation.

Doubtnut Promotions Banner
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • When the time taken to complete a given amount of work increases, then,

    Apower increases
    Bpower decreases
    Cenergy increases
    Denergy decreases
  • A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?

    Aa. 10%
    Bb. 1427%
    Cc. 20%
    Dd. can't be determined
  • A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?

    A10%
    B1427%
    C20%
    Dcan’t be determined