Fifteen men can build a wall in 60 days. How many more men are required to build another wall of same size in 45 days ?
The correct Answer is:5 men
To solve the problem step by step, we can use the concept of inverse variation. Here's how we can approach it:
Step 1: Understand the relationship between men, days, and work
We know that 15 men can build a wall in 60 days. This means that the amount of work done is constant.
Step 2: Set up the equation
Let x be the number of men required to build the wall in 45 days. According to the inverse variation principle, we can set up the relationship as follows:
Men×Days=Constant Work
For the first scenario:
15 men×60 days=Constant Work
For the second scenario:
x men×45 days=Constant Work
Step 3: Set the equations equal
Since both expressions equal the same constant work, we can write:
15×60=x×45
Step 4: Solve for x
Now we can solve for x:
900=x×45
To isolate x, divide both sides by 45:
x=90045
Calculating this gives:
x=20
Step 5: Determine how many more men are needed
We found that 20 men are required to build the wall in 45 days. However, we need to find out how many more men are required compared to the original 15 men.
More men required=x−15=20−15=5
Final Answer
Thus, 5 more men are required to build another wall of the same size in 45 days.
---
We know that 15 men can build a wall in 60 days. This means that the amount of work done is constant.
Let x be the number of men required to build the wall in 45 days. According to the inverse variation principle, we can set up the relationship as follows:
15 men×60 days=Constant Work
x men×45 days=Constant Work
Since both expressions equal the same constant work, we can write:
Now we can solve for x:
We found that 20 men are required to build the wall in 45 days. However, we need to find out how many more men are required compared to the original 15 men.
Thus, 5 more men are required to build another wall of the same size in 45 days.
Topper's Solved these Questions
- BOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (E)19videos
DIRECT AND INVERSE VARIATIONS
- BOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 C18videos
DIRECT AND INVERSE VARIATIONS
- BOOK - ICSECHAPTER - DATA HANDLING EXERCISE - EXERCISE 22 (B)10videos
DATA HANDLING
- BOOK - ICSECHAPTER - EXPONENTS (POWERS) EXERCISE - EXERCISE 2(B)50videos
EXPONENTS (POWERS)
Similar Questions
30 men can build a wall in 50 days. How many more men are required to build another wall, double in size,in 75 days?
View Solution15 men can build a 16.5 m long wall in one day. How many men are required to build 66 m long wall in one day?
View SolutionIf 5 men can build a wall in 12 days, how many men can build it in 10 days?
View SolutionIf 8 men can do a piece of work in 15 days, how many men are required to do the same piece of work in 10 days ?
View Solution50 labourers can dig a point in 16 days. How many labourers will be reuired to dig another pond, double in size, in 20 days ?
View SolutionIf 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours ?
View SolutionFour workers can build a house in 9 days. How many days would it takes 3 workers to build the same house?
View SolutionIf 15 workers can build a wall in 48 hours, how many workers will berequired to do the same work in 30 hours?
View SolutionHow many squares of each side 1 cm are required to build a square of side 8 cm ?
View SolutionA factory requires 42 machines to produce a given number of articles in 63 days. How many machines would be required to produce the same number of articles in 54 days?
View Solution