Find the cost of digging a cuboidal pit 8 m long, 6 m broad and 3 m deep at the rate ofRs 30 per m3.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To find the cost of digging a cuboidal pit, we will follow these steps:

Step 1: Calculate the Volume of the Cuboidal Pit
The formula for the volume V of a cuboid is given by:
V=length×breadth×depth
Given:
- Length =8m
- Breadth =6m
- Depth =3m

Substituting the values:
V=8m×6m×3m
V=144m3

Step 2: Calculate the Cost of Digging
The cost C of digging is calculated by multiplying the volume by the rate per cubic meter:
C=V×rate
Given:
- Volume V=144m3
- Rate =30R sperm3

Substituting the values:
C=144m3×30R s/m3
C=4320R s

Final Answer
The cost of digging the cuboidal pit is 4320R s.

---

Updated on:7/8/2024
|