Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elapsed time and idle times for each machine.
The correct Answer is:Total Elapsed Time T = 60 hours
Idle Time for machine X = 4 hours
Idle Time for machine Y = 6 hours
Topper's Solved these Questions
- QUESTION BANK 2021BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUESTION BANK 2021EXERCISE - Part II ASSIGNMENT PROBLEMS AND SEQUENCING (V. Activities)
2 Videos
- QUESTION BANK 2021BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUESTION BANK 2021EXERCISE - Part II PROBABILITY DISTRIBUTIONS (I. Choose the correct alternative.)
9 Videos
- QUESTION BANK 2021BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - QUESTION BANK 2021EXERCISE - Part II ASSIGNMENT PROBLEMS AND SEQUENCING (III. State whether each of the following is true or false.)
12 Videos
- PROBABILITY DISTRIBUTIONBOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - PROBABILITY DISTRIBUTIONEXERCISE - MULTIPLE CHOICE QUESTIONS
9 Videos
- THREE DIMENSIONAL GEOMETRY BOOK - NAVNEET PUBLICATION - MAHARASHTRA BOARDCHAPTER - THREE DIMENSIONAL GEOMETRY EXERCISE - MULTIPLE CHOICE QUESTIONS
8 Videos
Similar Questions
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours .
View SolutionFind the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in the order AB:
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
View Solution
Knowledge Check
The time elapsed between 33% and 67% completionb of a first order reaction is 30 minutes. What is the time needed for 25% completion?
A150.5 minutesB12.5 minutesC180.5 minutesD165.5 minutes
Solve the following problem of sequencing for minimizing the total elapsed time and idle time for both the machines.
The optimal sequence of the jobs as follows:
Total elapsed time is obtained as follows:
Total elapsed time T=□ minutes
Idle time for Machine A=T−□=□ minutes
Idle time for Machine B=□
View SolutionState True or False: The Total Elapsed is the time required to complete all the jobs i.e. entire task.
View SolutionA dice is throuwn two times and the total score in two throws is noted. Find the probability that the total score is :
6
View SolutionFive jobs must pass through a lathe and a surface grinder, in that order. The processing time in hours are shown below. Determine the optimal sequence of the jobs. Also, find the idle time of each machine:
View SolutionThe following table shows the frequency distribution of the time required for each worker to complete a work. From the table find the mean time required to complete the job for a worker.
View SolutionA dice is throuwn two times and the total score in two throws is noted. Find the probability that the total score is :
at least 6.
View SolutionA dice is thrown two times and the total score in two throws is noted. Find the probability that the total score is :
an even number
View Solution