Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elapsed time and idle times for each machine.
Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elapsed time and idle times for each machine.

Text Solution
Verified by Experts

The correct Answer is:Total Elapsed Time T = 60 hours
Idle Time for machine X = 4 hours
Idle Time for machine Y = 6 hours

Doubtnut Promotions Banner
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • The time elapsed between 33% and 67% completionb of a first order reaction is 30 minutes. What is the time needed for 25% completion?

    A150.5 minutes
    B12.5 minutes
    C180.5 minutes
    D165.5 minutes