If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?
52
31
13
65
The correct Answer is:A
To solve the problem step by step, we can use the concept of inverse proportionality between the number of men and the number of days required to complete the work.
Step 1: Understand the relationship between men and days
We know that if more men are working, the number of days required to complete the work will decrease. Conversely, if fewer men are working, the number of days required will increase. This means that the number of men and the number of days are inversely proportional.
Step 2: Calculate the total work in man-days
First, we need to calculate the total amount of work in terms of man-days. If 40 men can finish the work in 26 days, we can calculate the total work as follows:
Total Work=Number of Men×Number of Days=40 men×26 days=1040 man-days
Step 3: Determine the number of men required for 20 days
Now, we want to find out how many men are needed to complete the same amount of work (1040 man-days) in 20 days. Let x be the number of men required. We can set up the equation:
x men×20 days=1040 man-days
Step 4: Solve for x
To find x, we rearrange the equation:
x=1040 man-days20 days=52 men
Conclusion
Therefore, the number of men required to finish the work in 20 days is 52 men.
---
We know that if more men are working, the number of days required to complete the work will decrease. Conversely, if fewer men are working, the number of days required will increase. This means that the number of men and the number of days are inversely proportional.
First, we need to calculate the total amount of work in terms of man-days. If 40 men can finish the work in 26 days, we can calculate the total work as follows:
Total Work=Number of Men×Number of Days=40 men×26 days=1040 man-days
Now, we want to find out how many men are needed to complete the same amount of work (1040 man-days) in 20 days. Let x be the number of men required. We can set up the equation:
x men×20 days=1040 man-days
To find x, we rearrange the equation:
x=1040 man-days20 days=52 men
Therefore, the number of men required to finish the work in 20 days is 52 men.
Topper's Solved these Questions
- BOOK - RS AGGARWALCHAPTER - RATIO, PROPORTION AND UNITARY METHODEXERCISE - TEST PAPER-1019videos
RATIO, PROPORTION AND UNITARY METHOD
- BOOK - RS AGGARWALCHAPTER - RATIO, PROPORTION AND UNITARY METHODEXERCISE - EXERCISE 10C19videos
RATIO, PROPORTION AND UNITARY METHOD
- BOOK - RS AGGARWALCHAPTER - QUADRILATERALSEXERCISE - EXERCISE B (OBJECTIVE QUESTIONS)10videos
QUADRILATERALS
- BOOK - RS AGGARWALCHAPTER - SIMPLIFICATIONEXERCISE - Exercise2videos
SIMPLIFICATION
Similar Questions
Knowledge Check
- Question 1 - Select One
10 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?
A2B4C5D11 - Question 2 - Select One
100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
A100B60C80D40 - Question 3 - Select One
If x men can do a piece of work in y days, in how many days will x men do the same work ?
AxzyBxyzCyzxDxyz
40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?
View SolutionIf 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?
View SolutionIf 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?
View Solution20 Men can do a piece of work in 25 days, in how many days will 10 men do it?
View Solution