Doubtnut Promotions Sticky

If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?

A

52

B

31

C

13

D

65

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we can use the concept of inverse proportionality between the number of men and the number of days required to complete the work.

Step 1: Understand the relationship between men and days
We know that if more men are working, the number of days required to complete the work will decrease. Conversely, if fewer men are working, the number of days required will increase. This means that the number of men and the number of days are inversely proportional.

Step 2: Calculate the total work in man-days
First, we need to calculate the total amount of work in terms of man-days. If 40 men can finish the work in 26 days, we can calculate the total work as follows:
Total Work=Number of Men×Number of Days=40 men×26 days=1040 man-days

Step 3: Determine the number of men required for 20 days
Now, we want to find out how many men are needed to complete the same amount of work (1040 man-days) in 20 days. Let x be the number of men required. We can set up the equation:
x men×20 days=1040 man-days

Step 4: Solve for x
To find x, we rearrange the equation:
x=1040 man-days20 days=52 men

Conclusion
Therefore, the number of men required to finish the work in 20 days is 52 men.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    10 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?

    A2
    B4
    C5
    D11
  • Question 2 - Select One

    100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?

    A100
    B60
    C80
    D40
  • Question 3 - Select One

    If x men can do a piece of work in y days, in how many days will x men do the same work ?

    Axzy
    Bxyz
    Cyzx
    Dxyz