If 40 men complete a piece of work in 5 days, then 80 men can complete the same piece of work in _________.
The correct Answer is:2.5 days
Step by step video, text & image solution for If 40 men complete a piece of work in 5 days, then 80 men can complete the same piece of work in _________. by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO, PROPORTION AND VARIATIONEXERCISE - CONCEPT APPLICATION60videos
RATIO, PROPORTION AND VARIATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO, PROPORTION AND VARIATIONEXERCISE - EXAMPLE46videos
RATIO, PROPORTION AND VARIATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - PROFIT AND LOSS DISCOUNT AND PARTNERSHIP EXERCISE - CONCEPT APPLICATION (LEVEL 2)29videos
PROFIT AND LOSS DISCOUNT AND PARTNERSHIP
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - REAL NUMBERS AND LCM AND HCF EXERCISE - level -111videos
REAL NUMBERS AND LCM AND HCF
Similar Questions
If 40 men complete a piece of work in 5 days, then 80 man can complete the same piece of work in _____.
View Solution9 children can complete a piece of work in 360 days. 18 men can complete the same piece of work in72 days and 12 women can complete it in 162 days. In how many days can 4 men, 12 women and 10 children together complete the piece of work?
View Solution
Knowledge Check
- Question 1 - Select One
6 men or 10 boys can complete a piece of work in 15 days. If 7 men and x boys complete the same piece of work in 9 days, then x is equal to
A4B5C6D7 - Question 2 - Select One
Ten women can complete a picce of work in 15 days. Six men can complete the same piece of work in 10 days. In how many days can 5 women and six men together complete the piece of work?
A15 daysB7.5 daysC9 daysD12.5 days - Question 3 - Select One
2 men can complete a piece of work in 6 days. 2 women can
complete the same piece of work in 9 days. Where as 3
children can complete the same piece of work in 8 days. 3
women and 4 children worked together for 1 day. If only
men were to finish the remaining work in day, how many
total men would be required?A4B8C6Dcan't be determined
9 children can complete a plece of work in 360 days. 18 men can complete the same plece of work in 72 days and 12 women can complete the piece of work in 162 days. In how many days can 4 men, 12 women and 10 children together complete the piece of work?
View SolutionIn how many days 14 men can complete a piece of work?
I. If 18 women can complete the same piece of work in 24 days
II. If 28 children can complete the same piece of work in 56 days.View SolutionA alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?
View Solution8 men can complete a work in 12 days, 4 women can complete it in 48 days and 10 children can complete the same work in 24 days. In how many days can 10 men, 4 women and 10 children complete the same work?
View Solution4 man can complete a piece of work in 2 days. 4 wonen can
complete the same piece of work in 4 days whereas 5 children
can complete the same piece of work in 4 days. If, 2 men, 4
women and 10 children work together, in how many days
can the work be completed ?View Solution