Doubtnut Promotions Sticky

If 40 men complete a piece of work in 5 days, then 80 men can complete the same piece of work in _________.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:2.5 days

|
Answer

Step by step video, text & image solution for If 40 men complete a piece of work in 5 days, then 80 men can complete the same piece of work in _________. by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    6 men or 10 boys can complete a piece of work in 15 days. If 7 men and x boys complete the same piece of work in 9 days, then x is equal to

    A4
    B5
    C6
    D7
  • Question 2 - Select One

    Ten women can complete a picce of work in 15 days. Six men can complete the same piece of work in 10 days. In how many days can 5 women and six men together complete the piece of work?

    A15 days
    B7.5 days
    C9 days
    D12.5 days
  • Question 3 - Select One

    2 men can complete a piece of work in 6 days. 2 women can
    complete the same piece of work in 9 days. Where as 3
    children can complete the same piece of work in 8 days. 3
    women and 4 children worked together for 1 day. If only
    men were to finish the remaining work in day, how many
    total men would be required?

    A4
    B8
    C6
    Dcan't be determined