If took 12 men 5 hours to build an airstrip. Working at the same rate, how many additional men could have been hired in order for the job to have taken 1 hour less?
Two
Three
Four
Six
The correct Answer is:B
To solve the problem step by step, we need to determine how many additional men are required to complete the airstrip in 4 hours instead of 5 hours.
Step 1: Understand the initial conditions
We know that 12 men take 5 hours to build the airstrip.
Step 2: Calculate the total work done
The total work done can be calculated in terms of "man-hours."
- Total work = Number of men × Number of hours
- Total work = 12 men × 5 hours = 60 man-hours
Step 3: Determine the new time frame
We want to complete the same work in 1 hour less, which means we need to finish the work in 4 hours.
Step 4: Set up the equation for the new scenario
Let x be the additional men hired. Therefore, the total number of men working now will be 12+x.
The work done in the new scenario can also be expressed as:
- Total work = (Number of men) × (Number of hours)
- Total work = (12 + x) men × 4 hours
Step 5: Set the equation equal to the total work
Since the total work remains the same (60 man-hours), we can set up the equation:
(12+x)×4=60
Step 6: Solve for x
1. Expand the equation:
48+4x=60
2. Isolate 4x:
4x=60−48
4x=12
3. Divide by 4:
x=124=3
Conclusion
Thus, the number of additional men required is x=3.
We know that 12 men take 5 hours to build the airstrip.
The total work done can be calculated in terms of "man-hours."
- Total work = Number of men × Number of hours
- Total work = 12 men × 5 hours = 60 man-hours
We want to complete the same work in 1 hour less, which means we need to finish the work in 4 hours.
Let x be the additional men hired. Therefore, the total number of men working now will be 12+x.
- Total work = (Number of men) × (Number of hours)
- Total work = (12 + x) men × 4 hours
Since the total work remains the same (60 man-hours), we can set up the equation:
(12+x)×4=60
1. Expand the equation:
48+4x=60
2. Isolate 4x:
4x=60−48
4x=12
3. Divide by 4:
x=124=3
Thus, the number of additional men required is x=3.
Topper's Solved these Questions
- PROBLEM SOLVING AND DATA ANALYSISBOOK - ENGLISH SATCHAPTER - PROBLEM SOLVING AND DATA ANALYSISEXERCISE - Grib-In
40 Videos
- PROBLEM SOLVING AND DATA ANALYSISBOOK - ENGLISH SATCHAPTER - PROBLEM SOLVING AND DATA ANALYSISEXERCISE - Grib-In
40 Videos
- PROBLEM SOLVING AND DATA ANALYSISBOOK - ENGLISH SATCHAPTER - PROBLEM SOLVING AND DATA ANALYSISEXERCISE - EXERICSE
80 Videos
- PROBLEMS IN CONTEXT BOOK - ENGLISH SATCHAPTER - PROBLEMS IN CONTEXT EXERCISE - PRACTICE TEST
10 Videos
Similar Questions
If 5 men can build a wall in 12 days, how many men can build it in 10 days?
View SolutionThe first order reaction has k=1.5×10−6 per second at 200∘C . If the reaction is allowed to ruf for 10 hours at the same temperature, what percentage of the initial concentration would have changed into the product? What is the half life period of this reaction ?
View Solution
Knowledge Check
Laura can solve 6 math questions in 12 minutes. Working at the same rate, how many minutes would it take Laura to solve 5 math questions?
A6B9C10D11Ana and Amy started a landscaping job together. When Ana stopped, she had completed 25 of the job. When Amy stopped, she had completed 13 of the job. Then Ruben complete the rest of the job in 2 hours. Assume that Ana, Amy and Ruben all worked at the same rate. Which of the following values is closest to the number of hours it would have taken 1 of them to complete the entire job alone?
A0.37B1.27C2.73D7.50A plumber works twice as fast as his apprentice. After the plumber has worked alone for 3 hours, his apprentice joins him and working together they complete the job 4 hours later. How many hours would it have taken the plumber to do the entire job by himself?
A9B12C14D18
Eight men can dig a field 14 days,working 6 hours a day. In how many days can 7 men dig the same field, working 8 hours a day ?
View SolutionIf 15 workers can build a wall in 48 hours, how many workers will berequired to do the same work in 30 hours?
View SolutionIf 56 workers can build a wall in 180 hours, how many workers will be required to do the same work in 70 hours ?
View SolutionA contractor undertook to build a road in 200 days. He employed 140 men. After 60 days, he found that only one-fourth of the road could be built. How many additional men should he emp,oyed to complete the work in time ?
View SolutionTwelve typists, all working with same speed, type a certain number of pages in 18 days working 8 hours a day. Find, how many hours per day must sixteen typists work in order to type the same number of pages in 9 days ?
View Solution