Doubtnut Promotions Sticky

In order to complete a work in 28 days, 60 men are required. How Mny men will be required if the same work is to be completed in 40 days ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:42 men


To solve the problem step by step, we can use the concept of direct variation. The number of men required to complete a work is inversely proportional to the number of days taken to complete it.

Step 1: Understand the relationship
We know that if more days are taken to complete the same work, fewer men will be required. This is an inverse variation.

Step 2: Calculate the total work in man-days
To find out how many men are needed for different durations, we first calculate the total work in man-days required to complete the task in 28 days with 60 men.

Total work=Number of men×Number of days=60 men×28 days=1680 man-days

Step 3: Calculate the number of men needed for 40 days
Now, we need to find out how many men are required to complete the same amount of work (1680 man-days) in 40 days.

Let x be the number of men required.

Using the formula for total work:

Total work=Number of men×Number of days

We can set up the equation:

1680 man-days=x men×40 days

Step 4: Solve for x
Now, we can solve for x:

x=1680 man-days40 days=42 men

Final Answer
Therefore, 42 men will be required to complete the work in 40 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions