In order to complete a work in 28 days, 60 men are required. How Mny men will be required if the same work is to be completed in 40 days ?
The correct Answer is:42 men
To solve the problem step by step, we can use the concept of direct variation. The number of men required to complete a work is inversely proportional to the number of days taken to complete it.
Step 1: Understand the relationship
We know that if more days are taken to complete the same work, fewer men will be required. This is an inverse variation.
Step 2: Calculate the total work in man-days
To find out how many men are needed for different durations, we first calculate the total work in man-days required to complete the task in 28 days with 60 men.
Total work=Number of men×Number of days=60 men×28 days=1680 man-days
Step 3: Calculate the number of men needed for 40 days
Now, we need to find out how many men are required to complete the same amount of work (1680 man-days) in 40 days.
Let x be the number of men required.
Using the formula for total work:
Total work=Number of men×Number of days
We can set up the equation:
1680 man-days=x men×40 days
Step 4: Solve for x
Now, we can solve for x:
x=1680 man-days40 days=42 men
Final Answer
Therefore, 42 men will be required to complete the work in 40 days.
---
We know that if more days are taken to complete the same work, fewer men will be required. This is an inverse variation.
To find out how many men are needed for different durations, we first calculate the total work in man-days required to complete the task in 28 days with 60 men.
Now, we need to find out how many men are required to complete the same amount of work (1680 man-days) in 40 days.
Now, we can solve for x:
Therefore, 42 men will be required to complete the work in 40 days.
Topper's Solved these Questions
- BOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (D)13videos
DIRECT AND INVERSE VARIATIONS
- BOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (E)19videos
DIRECT AND INVERSE VARIATIONS
- BOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (B)11videos
DIRECT AND INVERSE VARIATIONS
- BOOK - ICSECHAPTER - DATA HANDLING EXERCISE - EXERCISE 22 (B)10videos
DATA HANDLING
- BOOK - ICSECHAPTER - EXPONENTS (POWERS) EXERCISE - EXERCISE 2(B)50videos
EXPONENTS (POWERS)
Similar Questions
If 8 men can do a piece of work in 15 days, how many men are required to do the same piece of work in 10 days ?
View SolutionIf 10 men take 6 days to construct a garage, how many more men are needed if the garage is to be constructed in 5 days ?
View Solution36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?
View Solution90 men can complete a work in 24 days working 8 hours a day. How many men are working 8 hours a day. How many men are required to complete the same work in 18 days working 712 hours a day ?
View SolutionA man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete it in 4 days ?
View SolutionAnil can do a piece of work in 5 days and ankur in 4 days. How long will they take to do the same work, if they work together?
View SolutionIf 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it ?
View Solution72 men do a piece of work in 25 days. In how many days will 30 men do the same work ?
View SolutionIf 78 men can do a work in 140 days, in how many days will 42 men do the same work ?
View Solution3 men and 4 boys can complete a certain amount of work in 28 days, whereas 4 men and 6 boys can complete the same work in 20 days. Find :
The number of days required by 7 men and 6 boys to complete the same work.View Solution