In sequencing problem the time which required to complete all the jobs i.e. entire task is called ….

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:Total Elapsed Time


Step-by-Step Solution:

1. Understanding the Problem: The question asks for the term used to describe the total time required to complete all jobs in a sequencing problem.

2. Identifying Key Terms: In the context of sequencing problems, we need to focus on the terminology related to time management and job completion.

3. Defining Total Elapsed Time: The total elapsed time refers to the cumulative time taken to finish all tasks or jobs in a sequence. It encompasses all the individual times required for each job.

4. Conclusion: Therefore, the answer to the question is "Total Elapsed Time".

Final Answer: Total Elapsed Time

---

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A30
    B40
    C25
    D50
  • 24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :

    A30
    B40
    C25
    D50
  • The amount of heat required to raise the temperature of the entire body by 1C is called

    Aspecific heat
    Blatent heat
    Cthermal capacity
    Dnone of these