P can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?
The correct Answer is:938days
To solve the problem of how many days P and Q can complete the work together, we can follow these steps:
Step 1: Determine the work done by P and Q in one day.
- P can complete the work in 25 days, so the work done by P in one day is:
Work done by P in one day=125
- Q can complete the work in 15 days, so the work done by Q in one day is:
Work done by Q in one day=115
Step 2: Calculate the total work done by P and Q together in one day.
- To find the total work done by both P and Q in one day, we add their individual work rates:
Total work in one day=125+115
Step 3: Find the LCM of the denominators.
- The denominators are 25 and 15. The least common multiple (LCM) of 25 and 15 can be calculated as follows:
- Prime factorization of 25: 52
- Prime factorization of 15: 3×5
- LCM = 3×52=75
Step 4: Convert the fractions to have a common denominator.
- Now we convert 125 and 115 to have a denominator of 75:
125=375(since 1×3=3 and 25×3=75)
115=575(since 1×5=5 and 15×5=75)
Step 5: Add the fractions.
- Now we can add the two fractions:
Total work in one day=375+575=875
Step 6: Calculate the total days to complete the work together.
- If P and Q can do 875 of the work in one day, the total number of days required to complete the work is the reciprocal of this value:
Total days=758
Step 7: Convert to mixed fraction.
- To convert 758 into a mixed fraction:
- Divide 75 by 8:
- 8×9=72 (which is the largest multiple of 8 less than 75)
- Remainder: 75−72=3
- Therefore, 758=938
Final Answer:
- P and Q together can complete the work in 938 days.
---
- P can complete the work in 25 days, so the work done by P in one day is:
Work done by P in one day=125
- Q can complete the work in 15 days, so the work done by Q in one day is:
Work done by Q in one day=115
- To find the total work done by both P and Q in one day, we add their individual work rates:
Total work in one day=125+115
- The denominators are 25 and 15. The least common multiple (LCM) of 25 and 15 can be calculated as follows:
- Prime factorization of 25: 52
- Prime factorization of 15: 3×5
- LCM = 3×52=75
- Now we convert 125 and 115 to have a denominator of 75:
125=375(since 1×3=3 and 25×3=75)
115=575(since 1×5=5 and 15×5=75)
- Now we can add the two fractions:
Total work in one day=375+575=875
- If P and Q can do 875 of the work in one day, the total number of days required to complete the work is the reciprocal of this value:
Total days=758
- To convert 758 into a mixed fraction:
- Divide 75 by 8:
- 8×9=72 (which is the largest multiple of 8 less than 75)
- Remainder: 75−72=3
- Therefore, 758=938
- P and Q together can complete the work in 938 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - ESSAY TYPE QUESTIONS18videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - CONCEPT APPLICATION (LEVEL 1)33videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - VERY SHORT ANSWER TYPE QUESTIONS30videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - NUMBER SYSTEMEXERCISE - ASSESSMENT TESTS24videos
NUMBER SYSTEM
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - Set theoryEXERCISE - ASSESSMENT TEST Test 212videos
Set theory
Similar Questions
A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
View SolutionIf A can do a work in 10 days and B can do the same work in 15 days, then how many days will they take to complete the work both while working together?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
A819B989C889D918 - Question 2 - Select One
A can do 110 th of a piece of work in a day. B can do the same work in 15 days. In how many days can they do the same work, working together?
A5B6C8D9 - Question 3 - Select One
A can do 110 th of a piece of work in a day. B can do the same work in 15 days. In how many days can they do the same work, working together?
A5B6C8D9
A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View Solution(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
View SolutionA can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?
View SolutionP can do a piece of work in 7 days and Q can do the same work in 21 days. How many days will both take together to complete the same work?
(a)4.75
(b)5.75
(c)6
(d)5.25View Solution