The following steps are involved in finding the total time taken by both A and B together to complete a work, when A takes 4 days and B takes 12 days to complete the work individually. Arrange them in sequential order.
(A) A and B's 1 day work = 14+112=412=13.
(B) Both A and B together can complete the entire work in 3 days.
(C) A's 1 day work = 14. B's 1 day work = 112.

A

ABC

B

CAB

C

CBA

D

ACB

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for The following steps are involved in finding the total time taken by both A and B together to complete a work, when A takes 4 days and B takes 12 days to complete the work individually. Arrange them in sequential order. (A) A and B's 1 day work = (1)/(4) + (1)/(12) = (4)/(12) = (1)/(3). (B) therefore Both A and B together can complete the entire work in 3 days. (C) A's 1 day work = (1)/(4). B's 1 day work = (1)/(12). by Maths experts to help you in doubts & scoring excellent marks in Class 7 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • The following steps are involved in finding the total time taken by both A and B together to complete a work, when A takes 4 days and B takes 12 days to complete the work individually. Arrange them in sequential order.
    (A) A and B's 1 day work = 14+112=412=13.
    (B) Both A and B together can complete the entire work in 3 days.
    (C) A's 1 day work = 14. B's 1 day work = 112.

    AABC
    BCAB
    CCBA
    DACB
  • B is twice efficient than A and the total time taken to complete the work by both A and B together is 22 days. Find the number of days taken by B to complete the work alone.

    A11 days
    B44 days
    C33 days
    D30 days
  • A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?

    A18 days
    B24 days
    C16 days
    D20 days