Doubtnut Promotions Sticky

The following table shows the frequency distribution of the time required for each worker to complete a work. From the table find the mean time required to complete the job for a worker.
The following table shows the frequency distribution of the time required for each worker to complete a work. From the table find the mean time required to complete the job for a worker.

Video Solution
Text Solution
Verified by Experts

The correct Answer is:25.3hrs

|
Answer

Step by step video & image solution for The following table shows the frequency distribution of the time required for each worker to complete a work. From the table find the mean time required to complete the job for a worker. by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men complete a work in 16 days. If 24 men are employed, then the time required to complete that work will be

    A7 days
    B8 days
    C10 days
    D12 days
  • Question 2 - Select One

    If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.

    A125 days
    B122 days
    C120 days
    D116 days