Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:36

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days? by Maths experts to help you in doubts & scoring excellent marks in Class 7 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?

    A28
    B21
    C14
    D7
  • If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22
  • 10 men can make a wall in 8 days. How many men required to complete the same work in half day

    A80
    B100
    C120
    D160