Doubtnut Promotions Sticky

Two workers A and B are engaged to do a piece of work. Working alone, A takes 8 hours more to complete the work than if both worked together. On the other hand, working alone, B would need 412 hours more to complete the work than if both worked together. How much time would they take to complete the job working together?

A

4Hours

B

5Hours

C

6 Hours

D

7 Hours

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C


If A & B work together take time t hr. If A work alone takes t+8hr.to complete the work
Work /hr by A is 1t+8 Similarly for B work/hr is 1t+9/2
When A & B work together there work/hr 1t+8+1t+9/2 Work will be done in t hr.
t(1t+8+1t+9/2)=1
By solving t=6

|
Updated on:21/07/2023

Related Playlists


Similar Questions