12 men can finish a piece of work in 25 days. The number of days in which the same piece of work can be done by 20 men, is (a) 10 days (b) 12 days (c) 15 days (d) 14 days
To solve the problem, we need to find out how many days it will take for 20 men to complete the same piece of work that 12 men can finish in 25 days.
1. Calculate the Total Work Done:
We first determine the total amount of work done in terms of "man-days".
- If 12 men can finish the work in 25 days, the total work (in man-days) is:
Total Work=Number of Men×Number of Days=12 men×25 days=300 man-days
2. Set Up the Equation for 20 Men:
Now, we need to find out how many days (let's call it x) it will take for 20 men to complete the same amount of work (300 man-days).
- The equation will be:
Total Work=Number of Men×Number of Days
300 man-days=20 men×x days
3. Solve for x:
Rearranging the equation to solve for x:
x=300 man-days20 men=15 days
4. Conclusion:
Therefore, it will take 20 men 15 days to complete the same piece of work.
Answer:
The number of days in which the same piece of work can be done by 20 men is 15 days (option c).
---
We first determine the total amount of work done in terms of "man-days".
- If 12 men can finish the work in 25 days, the total work (in man-days) is:
Total Work=Number of Men×Number of Days=12 men×25 days=300 man-days
Now, we need to find out how many days (let's call it x) it will take for 20 men to complete the same amount of work (300 man-days).
- The equation will be:
Total Work=Number of Men×Number of Days
300 man-days=20 men×x days
Rearranging the equation to solve for x:
x=300 man-days20 men=15 days
Therefore, it will take 20 men 15 days to complete the same piece of work.
The number of days in which the same piece of work can be done by 20 men is 15 days (option c).
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :
A38B28C19D17 - Question 2 - Select One
If x men can do a piece of work In x days, then the number of days in which y men can do the same work is
Axy daysBy2x daysCx2y daysDx2y days - Question 3 - Select One
If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be
A12 daysB10 daysC9 daysD8 days
If 6 men can do a piece of work in 8 days, then find the number of days in which 8 men can do the same work.
View SolutionIf 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?
View SolutionIf 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.
View Solution20 Men can do a piece of work in 25 days, in how many days will 10 men do it?
View Solution12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
View Solution