Doubtnut Promotions Sticky

12 men can finish a piece of work in 25 days. The number of days in which the same piece of work can be done by 20 men, is (a) 10 days      (b)  12 days   (c)  15 days         (d)   14 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to find out how many days it will take for 20 men to complete the same piece of work that 12 men can finish in 25 days.

1. Calculate the Total Work Done:
We first determine the total amount of work done in terms of "man-days".
- If 12 men can finish the work in 25 days, the total work (in man-days) is:
Total Work=Number of Men×Number of Days=12 men×25 days=300 man-days

2. Set Up the Equation for 20 Men:
Now, we need to find out how many days (let's call it x) it will take for 20 men to complete the same amount of work (300 man-days).
- The equation will be:
Total Work=Number of Men×Number of Days
300 man-days=20 men×x days

3. Solve for x:
Rearranging the equation to solve for x:
x=300 man-days20 men=15 days

4. Conclusion:
Therefore, it will take 20 men 15 days to complete the same piece of work.

Answer:
The number of days in which the same piece of work can be done by 20 men is 15 days (option c).

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :

    A38
    B28
    C19
    D17
  • Question 2 - Select One

    If x men can do a piece of work In x days, then the number of days in which y men can do the same work is

    Axy days
    By2x days
    Cx2y days
    Dx2y days
  • Question 3 - Select One

    If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be

    A12 days
    B10 days
    C9 days
    D8 days