A and B can do a piece of work in 6 days and 4 days respectively. A started the work, worked at it for 2 days and then was joined by B. Find the total time taken to complete the work.
To solve the problem step by step, let's follow the outlined process:
Step 1: Determine the work done by A and B in one day.
- A can complete the work in 6 days, so the work done by A in one day is:
Work done by A in one day=16
- B can complete the work in 4 days, so the work done by B in one day is:
Work done by B in one day=14
Step 2: Calculate the total work done by A in 2 days.
- In 2 days, A will complete:
Work done by A in 2 days=2×16=26=13
Step 3: Determine the remaining work after A has worked for 2 days.
- The total work is considered as 1 (whole work). After A has completed 13 of the work, the remaining work is:
Remaining work=1−13=23
Step 4: Calculate the combined work done by A and B together.
- When B joins A, their combined work in one day is:
Combined work of A and B=16+14
To add these fractions, find a common denominator (which is 12):
Combined work=212+312=512
Step 5: Determine how many days A and B will take to complete the remaining work.
- The remaining work is 23. To find the number of days (let's call it x) required to complete this remaining work at the rate of 512 per day, we set up the equation:
x×512=23
Solving for x:
x=2/35/12=23×125=2415=85 days
Step 6: Convert the days into a mixed number.
- 85 days can be expressed as:
1 day and 35 of a day
35 of a day is equivalent to:
35×24 hours=14.4 hours≈14 hours and 24 minutes
Step 7: Calculate the total time taken to complete the work.
- The total time taken is the time A worked alone plus the time A and B worked together:
Total time=2 days+85 days=2+1.6=3.6 days
Which can be expressed as:
3 days and 14.4 hours≈3 days and 14 hours and 24 minutes
Final Answer:
The total time taken to complete the work is approximately 3 days and 14 hours and 24 minutes.
---
- A can complete the work in 6 days, so the work done by A in one day is:
Work done by A in one day=16
- B can complete the work in 4 days, so the work done by B in one day is:
Work done by B in one day=14
- In 2 days, A will complete:
Work done by A in 2 days=2×16=26=13
- The total work is considered as 1 (whole work). After A has completed 13 of the work, the remaining work is:
Remaining work=1−13=23
- When B joins A, their combined work in one day is:
Combined work of A and B=16+14
To add these fractions, find a common denominator (which is 12):
Combined work=212+312=512
- The remaining work is 23. To find the number of days (let's call it x) required to complete this remaining work at the rate of 512 per day, we set up the equation:
x×512=23
Solving for x:
x=2/35/12=23×125=2415=85 days
- 85 days can be expressed as:
1 day and 35 of a day
35 of a day is equivalent to:
35×24 hours=14.4 hours≈14 hours and 24 minutes
- The total time taken is the time A worked alone plus the time A and B worked together:
Total time=2 days+85 days=2+1.6=3.6 days
Which can be expressed as:
3 days and 14.4 hours≈3 days and 14 hours and 24 minutes
The total time taken to complete the work is approximately 3 days and 14 hours and 24 minutes.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 6 days and 4 days respectively. A started the work, worked at it for 2 days and then was joined by B. Find the total time taken to complete the work.
View SolutionA and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 days - Question 2 - Select One
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 days - Question 3 - Select One
A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?
A9 daysB18 daysC6 daysD4 days
A and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?
View SolutionA and B can do a work in 15 days and 20 days respectively B started the work and they work on alternate days. Find the number of days it will take them to complete the work.
View SolutionA and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View SolutionA and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?View SolutionA and B can do a piece of work in 24 and 30 days respectively.
Both started the work and worked for 6 days. Then B leaves
the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
alone can do the workView Solution