Doubtnut Promotions Sticky

A and B can do a piece of work in 6 days and 4 days respectively. A started the work, worked at it for 2 days and then was joined by B. Find the total time taken to complete the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's follow the outlined process:

Step 1: Determine the work done by A and B in one day.
- A can complete the work in 6 days, so the work done by A in one day is:
Work done by A in one day=16

- B can complete the work in 4 days, so the work done by B in one day is:
Work done by B in one day=14

Step 2: Calculate the total work done by A in 2 days.
- In 2 days, A will complete:
Work done by A in 2 days=2×16=26=13

Step 3: Determine the remaining work after A has worked for 2 days.
- The total work is considered as 1 (whole work). After A has completed 13 of the work, the remaining work is:
Remaining work=113=23

Step 4: Calculate the combined work done by A and B together.
- When B joins A, their combined work in one day is:
Combined work of A and B=16+14
To add these fractions, find a common denominator (which is 12):
Combined work=212+312=512

Step 5: Determine how many days A and B will take to complete the remaining work.
- The remaining work is 23. To find the number of days (let's call it x) required to complete this remaining work at the rate of 512 per day, we set up the equation:
x×512=23
Solving for x:
x=2/35/12=23×125=2415=85 days

Step 6: Convert the days into a mixed number.
- 85 days can be expressed as:
1 day and 35 of a day
35 of a day is equivalent to:
35×24 hours=14.4 hours14 hours and 24 minutes

Step 7: Calculate the total time taken to complete the work.
- The total time taken is the time A worked alone plus the time A and B worked together:
Total time=2 days+85 days=2+1.6=3.6 days
Which can be expressed as:
3 days and 14.4 hours3 days and 14 hours and 24 minutes

Final Answer:
The total time taken to complete the work is approximately 3 days and 14 hours and 24 minutes.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • Question 2 - Select One

    A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • Question 3 - Select One

    A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?

    A9 days
    B18 days
    C6 days
    D4 days