A constrator employed 210 men to build a house in 60 days. After 12 days.he was joined by 70 more men. In how many days will the remaining work be finished?
Hint. 210 men can complete the remaning work in 48 days.Find in how many days 280 men can do it.
The correct Answer is:36 days
To solve the problem step by step, we will follow the hints provided and use the unitary method.
Step 1: Calculate the total work done by 210 men in 12 days.
- Total work can be represented in terms of man-days.
- If 210 men can complete the work in 60 days, the total work is:
Total Work=210 men×60 days=12600 man-days
Step 2: Calculate the work done in the first 12 days.
- In 12 days, the work done by 210 men is:
Work done in 12 days=210 men×12 days=2520 man-days
Step 3: Calculate the remaining work.
- The remaining work after 12 days is:
Remaining Work=Total Work−Work done in 12 days
Remaining Work=12600 man-days−2520 man-days=10080 man-days
Step 4: Determine the new workforce.
- After 12 days, 70 more men join the original 210 men, making the total number of men:
Total Men=210+70=280 men
Step 5: Calculate the time taken by 280 men to complete the remaining work.
- If 280 men are working, we need to find out how many days it will take to complete 10080 man-days of work:
Days=Remaining WorkTotal Men=10080 man-days280 men=36 days
Final Answer:
The remaining work will be finished in 36 days.
---
- Total work can be represented in terms of man-days.
- If 210 men can complete the work in 60 days, the total work is:
Total Work=210 men×60 days=12600 man-days
- In 12 days, the work done by 210 men is:
Work done in 12 days=210 men×12 days=2520 man-days
- The remaining work after 12 days is:
Remaining Work=Total Work−Work done in 12 days
Remaining Work=12600 man-days−2520 man-days=10080 man-days
- After 12 days, 70 more men join the original 210 men, making the total number of men:
Total Men=210+70=280 men
- If 280 men are working, we need to find out how many days it will take to complete 10080 man-days of work:
Days=Remaining WorkTotal Men=10080 man-days280 men=36 days
The remaining work will be finished in 36 days.
Topper's Solved these Questions
- BOOK - RS AGGARWALCHAPTER - UNITARY METHODEXERCISE - EXERCISE-9-C16videos
UNITARY METHOD
- BOOK - RS AGGARWALCHAPTER - UNITARY METHODEXERCISE - TEST PAPER -918videos
UNITARY METHOD
- BOOK - RS AGGARWALCHAPTER - UNITARY METHODEXERCISE - EXERCISE-9A15videos
UNITARY METHOD
- BOOK - RS AGGARWALCHAPTER - THREE -DIMENSIONAL SHAPESEXERCISE - Execise1videos
THREE -DIMENSIONAL SHAPES
Similar Questions
Knowledge Check
- Question 1 - Select One
12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?
A18B12C24DCannot be determined - Question 2 - Select One
If 45 men can do a piece of work in 49 days, in how many days will 35 men do it?
A63B53C43D33 - Question 3 - Select One
45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?
A10B16C18D15
If 52 men can do a piece of work in 35 days, in how many days 28 men will do it ?
View Solution12 men can complete one third of the work in 8 days. In how many days can 16 men complete that work?
View Solution20 Men can do a piece of work in 25 days, in how many days will 10 men do it?
View Solution5 men can complete a job in 8 days. How many days will it take if 12 men do the job?
View Solution34 men can do a piece of work in 12 days . How many days will 51 men take to do it
View Solution