10 men can finish the construction of a wall in 8 days.How many men are added to finish the work in half a day ?
80
100
120
0.625
The correct Answer is:d
To solve the problem step by step, we will use the concept of the Unitary Method and the idea of indirect proportion.
1. Understand the given information:
- 10 men can finish the construction of a wall in 8 days.
2. Calculate the total work in man-days:
- Total work = Number of men × Number of days
- Total work = 10 men × 8 days = 80 man-days.
3. Determine the required time to finish the work:
- We need to find out how many men are required to finish the same work in half a day (0.5 days).
4. Set up the equation using the concept of man-days:
- Let the number of men required to finish the work in half a day be x.
- Total work = Number of men × Number of days
- Therefore, 80 man-days = x men × 0.5 days.
5. Solve for x:
- Rearranging the equation gives:
x=80 man-days0.5 days=80÷0.5=160 men.
6. Calculate how many men are added:
- We initially had 10 men.
- Men added = Total men required - Initial men
- Men added = 160 men - 10 men = 150 men.
Final Answer:
150 men need to be added to finish the construction of the wall in half a day.
---
- 10 men can finish the construction of a wall in 8 days.
- Total work = Number of men × Number of days
- Total work = 10 men × 8 days = 80 man-days.
- We need to find out how many men are required to finish the same work in half a day (0.5 days).
- Let the number of men required to finish the work in half a day be x.
- Total work = Number of men × Number of days
- Therefore, 80 man-days = x men × 0.5 days.
- Rearranging the equation gives:
x=80 man-days0.5 days=80÷0.5=160 men.
- We initially had 10 men.
- Men added = Total men required - Initial men
- Men added = 160 men - 10 men = 150 men.
150 men need to be added to finish the construction of the wall in half a day.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
10 men can make a wall in 8 days. How many men required to complete the same work in half day
A80B100C120D160 - Question 2 - Select One
10 men can finish painting a wall in 8 days. How many more men will be needed if the painting work is to be finished in 4 days?
A8B5C10D20 - Question 3 - Select One
If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?
A52B31C13D65
40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution6 men and 8 women can finish construction of a road in 10 days, 26 men and 48 women can finish this in 2 days. If 15 men and 20 women are appointed for completing this task, then how many days do they need?
View Solution30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution