Doubtnut Promotions Sticky

10 men can finish the construction of a wall in 8 days.How many men are added to finish the work in half a day ?

A

80

B

100

C

120

D

0.625

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:d


To solve the problem step by step, we will use the concept of the Unitary Method and the idea of indirect proportion.

1. Understand the given information:
- 10 men can finish the construction of a wall in 8 days.

2. Calculate the total work in man-days:
- Total work = Number of men × Number of days
- Total work = 10 men × 8 days = 80 man-days.

3. Determine the required time to finish the work:
- We need to find out how many men are required to finish the same work in half a day (0.5 days).

4. Set up the equation using the concept of man-days:
- Let the number of men required to finish the work in half a day be x.
- Total work = Number of men × Number of days
- Therefore, 80 man-days = x men × 0.5 days.

5. Solve for x:
- Rearranging the equation gives:
x=80 man-days0.5 days=80÷0.5=160 men.

6. Calculate how many men are added:
- We initially had 10 men.
- Men added = Total men required - Initial men
- Men added = 160 men - 10 men = 150 men.

Final Answer:
150 men need to be added to finish the construction of the wall in half a day.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    10 men can make a wall in 8 days. How many men required to complete the same work in half day

    A80
    B100
    C120
    D160
  • Question 2 - Select One

    10 men can finish painting a wall in 8 days. How many more men will be needed if the painting work is to be finished in 4 days?

    A8
    B5
    C10
    D20
  • Question 3 - Select One

    If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?

    A52
    B31
    C13
    D65