P can complete a job in 60 days while Q can compelete in 90 days. With the help of R, They completed in 20 days. If they earned a total of Rs. 3600, then find R is share (in Rs.)
1360
1600
1480
1540
The correct Answer is:B
To solve the problem step by step, we will first determine the work done by P, Q, and R, and then calculate R's share of the earnings.
Step 1: Calculate the work done by P and Q
- P can complete the job in 60 days. Therefore, P's work per day = 1/60 of the job.
- Q can complete the job in 90 days. Therefore, Q's work per day = 1/90 of the job.
Step 2: Find the combined work of P and Q
- The combined work of P and Q in one day = (1/60 + 1/90).
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 60 and 90 is 180.
- Convert the fractions:
- P's work = 1/60 = 3/180
- Q's work = 1/90 = 2/180
- Therefore, combined work of P and Q = (3/180 + 2/180) = 5/180 = 1/36 of the job per day.
Step 3: Calculate the total work done by P, Q, and R together
- Let R's work per day be denoted as R.
- Together, they completed the job in 20 days, so their combined work per day is:
- Total work done in 20 days = 1 job, hence work done per day = 1/20 of the job.
- Therefore, we can set up the equation:
- (1/36 + R) = 1/20.
Step 4: Solve for R's work
- To solve for R, we need to find a common denominator for 36 and 20, which is 180.
- Rewrite the equation:
- (5/180 + R) = (9/180).
- Subtract (5/180) from both sides:
- R = (9/180 - 5/180) = 4/180 = 1/45 of the job per day.
Step 5: Calculate the total efficiency of P, Q, and R
- The efficiencies are:
- P's efficiency = 1/60
- Q's efficiency = 1/90
- R's efficiency = 1/45
- Convert these to a common unit:
- P's efficiency = 3 units (in 180)
- Q's efficiency = 2 units (in 180)
- R's efficiency = 4 units (in 180)
- Total efficiency = 3 + 2 + 4 = 9 units.
Step 6: Calculate R's share of the earnings
- Total earnings = Rs. 3600.
- R's share of the total efficiency = (R's efficiency / Total efficiency) * Total earnings.
- R's share = (4/9) * 3600 = 1600.
Final Answer
R's share is Rs. 1600.
---
- P can complete the job in 60 days. Therefore, P's work per day = 1/60 of the job.
- Q can complete the job in 90 days. Therefore, Q's work per day = 1/90 of the job.
- The combined work of P and Q in one day = (1/60 + 1/90).
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 60 and 90 is 180.
- Convert the fractions:
- P's work = 1/60 = 3/180
- Q's work = 1/90 = 2/180
- Therefore, combined work of P and Q = (3/180 + 2/180) = 5/180 = 1/36 of the job per day.
- Let R's work per day be denoted as R.
- Together, they completed the job in 20 days, so their combined work per day is:
- Total work done in 20 days = 1 job, hence work done per day = 1/20 of the job.
- Therefore, we can set up the equation:
- (1/36 + R) = 1/20.
- To solve for R, we need to find a common denominator for 36 and 20, which is 180.
- Rewrite the equation:
- (5/180 + R) = (9/180).
- Subtract (5/180) from both sides:
- R = (9/180 - 5/180) = 4/180 = 1/45 of the job per day.
- The efficiencies are:
- P's efficiency = 1/60
- Q's efficiency = 1/90
- R's efficiency = 1/45
- Convert these to a common unit:
- P's efficiency = 3 units (in 180)
- Q's efficiency = 2 units (in 180)
- R's efficiency = 4 units (in 180)
- Total efficiency = 3 + 2 + 4 = 9 units.
- Total earnings = Rs. 3600.
- R's share of the total efficiency = (R's efficiency / Total efficiency) * Total earnings.
- R's share = (4/9) * 3600 = 1600.
R's share is Rs. 1600.
Topper's Solved these Questions
Similar Questions
a can complete a piece of work in 15 days. B can complete it in 10 days. With the help C, they can complete it in 4 days. They all worked togther and earned a total of s. 750. Find C's share.
View SolutionA alone can complete a work ₹ 6,500 in 15 days. With the help of B the work is completed in 12 days. the share of B is
View Solution
Knowledge Check
- Question 1 - Select One
P,Q and R can complete a job in 6 days, 9 days and 12 days, respectively. They worked together and completed it. They earned a total of Rs. 2600. Find P's share ( in Rs.)
A1350B1500C9000D1200 - Question 2 - Select One
If 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.
A3B10C12D4 - Question 3 - Select One
A and B were assigned to do a job for an amount of 1200. A alone can do it in 15 days, while B can do it in 12 days. With the help of C, they can finish in 5 days. The share of amount that C earns is
Aa)Rs 300Bb)Rs 400Cc)Rs 500Dd)Rs 600
P alone can complete a piece of work in 12 days and Q can complete the same work in 18 days. With the help of R, all
three finish the work in 6 days. In how many days can R alone complete the work?View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View Solution22 men can complete a job in 16days. In how many days, will 32 men complete that job?
View SolutionP and Q can do a piece of work in 12 days 16 days, resepetively. With the help of R, they completed the work in 5 days and earn Rs. 912. What is the share of R?
View SolutionA alone can do a piece of work in 12 days and B can do the same work in 15 days. If they complete the work together and receive a total amount of Rs. 1800, then find the share of B.
View Solution