25 men can reap a field in 20 days. When should 15men leave the work, if the whole field is to be reaped in 35 days after they leave the work?
After 5 days
After 10 days
After 9 days
After 7 days
The correct Answer is:A
To solve the problem step by step, we will use the concept of work done and the unitary method.
Step 1: Calculate the total work in man-days.
Given that 25 men can reap a field in 20 days, we can calculate the total work in man-days as follows:
Total work = Number of men × Number of days
Total work = 25 men × 20 days = 500 man-days
Step 2: Determine the work done by 15 men.
Next, we need to find out how much work 15 men can do in a certain number of days. Let’s denote the number of days that 15 men work before they leave as x.
Work done by 15 men in x days = 15 men × x days = 15x man-days
Step 3: Calculate the remaining work after 15 men leave.
After 15 men leave, the remaining work will be:
Remaining work = Total work - Work done by 15 men
Remaining work = 500 man-days - 15x man-days
Step 4: Determine the work done by the remaining men.
After 15 men leave, there will be 10 men left (since 25 - 15 = 10 men). We know that the remaining work must be completed in 35 days.
Work done by 10 men in 35 days = 10 men × 35 days = 350 man-days
Step 5: Set up the equation.
Now we can set up the equation for the remaining work:
Remaining work = Work done by 10 men in 35 days
500 - 15x = 350
Step 6: Solve for x.
Now we will solve the equation for x:
500 - 15x = 350
=> 15x = 500 - 350
=> 15x = 150
=> x = 150 / 15
=> x = 10
Conclusion:
15 men should leave the work after 10 days.
Given that 25 men can reap a field in 20 days, we can calculate the total work in man-days as follows:
Total work = 25 men × 20 days = 500 man-days
Next, we need to find out how much work 15 men can do in a certain number of days. Let’s denote the number of days that 15 men work before they leave as x.
After 15 men leave, the remaining work will be:
Remaining work = 500 man-days - 15x man-days
After 15 men leave, there will be 10 men left (since 25 - 15 = 10 men). We know that the remaining work must be completed in 35 days.
Now we can set up the equation for the remaining work:
500 - 15x = 350
Now we will solve the equation for x:
=> 15x = 500 - 350
=> 15x = 150
=> x = 150 / 15
=> x = 10
15 men should leave the work after 10 days.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - UNITARY METHODEXERCISE - EXERCISE BASE LEVEL QUESTIONS22videos
UNITARY METHOD
- BOOK - ARIHANT SSCCHAPTER - TRUE DISCOUNT AND BANKER'S DISCOUNTEXERCISE - FAST TRACK PRACTICE23videos
TRUE DISCOUNT AND BANKER'S DISCOUNT
- BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE111videos
VOLUME AND SURFACE AREA
Similar Questions
Knowledge Check
- Question 1 - Select One
25 men reap a field in 20 days. When should 15 men leave the work, if the whole field is to be reaped in 3712 days after they leave the work?
A6 daysB4 daysC5 daysDNone of these - Question 2 - Select One
35 men can reap a field in 8 days. In how many days can 20 men reap it?
A14 dayB28 dayC8712 dayDnon of these - Question 3 - Select One
12 men can reap a field in 25 days. In how many days can 20 men reap the same field?
A65 daysB35 daysC15 daysD25 days
If 35 men can reap a field in 8 days, in how many days can 20 men reap the same field?
View SolutionIf 16 men can reap a field in 30 days.in how many days will 20 men reap the same field?
View SolutionIf 16 men can reap a field in 30 days.in how many days will 20 men reap the same field?
View SolutionIf 16 men can rep a field in 30 days.in how many days will 20 men reap the same field?
View SolutionIf 20 men can reap a field in 38 days, in how many days will 19 men reap the field?
View Solution