In how many days will B alone complete the work?
I. A and B together can complete the work in 8 days. II. B and C together can complete the work in 10 days.
III. A and C together can complete the work in 12 days
Only I and II
Only II and II
I, II and III
Data is insufficient
The correct Answer is:C
To determine how many days B alone will take to complete the work, we can analyze the information given in the statements step by step.
Step 1: Understand the Work Rates
Let's denote:
- The total work as 1 unit.
- The rate of work done by A as A (units of work per day).
- The rate of work done by B as B (units of work per day).
- The rate of work done by C as C (units of work per day).
Step 2: Analyze Statement I
From Statement I, we know:
- A and B together can complete the work in 8 days.
- Therefore, their combined work rate is:
A+B=18 (units of work per day)
Step 3: Analyze Statement II
From Statement II, we know:
- B and C together can complete the work in 10 days.
- Therefore, their combined work rate is:
B+C=110 (units of work per day)
Step 4: Analyze Statement III
From Statement III, we know:
- A and C together can complete the work in 12 days.
- Therefore, their combined work rate is:
A+C=112 (units of work per day)
Step 5: Set Up the Equations
Now we have three equations:
1. A+B=18
2. B+C=110
3. A+C=112
Step 6: Solve the Equations
To find the individual work rates, we can manipulate these equations.
- From equations (1) and (2), we can express A and C in terms of B:
- From (1): A=18−B
- From (2): C=110−B
Substituting these into equation (3):
(18−B)+(110−B)=112
Step 7: Combine and Solve
Combining the left side:
18+110−2B=112
Finding a common denominator (which is 120):
15120+12120−2B=10120
27120−2B=10120
Rearranging gives:
2B=27120−10120=17120
B=17240
Step 8: Calculate Days for B Alone
To find the number of days B alone will take to complete the work:
Days for B=1B=117240=24017≈14.12 days
Thus, B alone will complete the work in approximately 14.12 days.
Conclusion
The answer is that B alone will complete the work in approximately 14.12 days.
Let's denote:
- The total work as 1 unit.
- The rate of work done by A as A (units of work per day).
- The rate of work done by B as B (units of work per day).
- The rate of work done by C as C (units of work per day).
From Statement I, we know:
- A and B together can complete the work in 8 days.
- Therefore, their combined work rate is:
A+B=18 (units of work per day)
From Statement II, we know:
- B and C together can complete the work in 10 days.
- Therefore, their combined work rate is:
B+C=110 (units of work per day)
From Statement III, we know:
- A and C together can complete the work in 12 days.
- Therefore, their combined work rate is:
A+C=112 (units of work per day)
Now we have three equations:
1. A+B=18
2. B+C=110
3. A+C=112
To find the individual work rates, we can manipulate these equations.
- From (1): A=18−B
- From (2): C=110−B
(18−B)+(110−B)=112
Combining the left side:
18+110−2B=112
15120+12120−2B=10120
27120−2B=10120
2B=27120−10120=17120
B=17240
To find the number of days B alone will take to complete the work:
Days for B=1B=117240=24017≈14.12 days
The answer is that B alone will complete the work in approximately 14.12 days.
Topper's Solved these Questions
Similar Questions
Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?
View SolutionA alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View Solution
Knowledge Check
- Question 1 - Select One
P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
A40B72C84D90 - Question 2 - Select One
P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
A1800B900C1200D1500 - Question 3 - Select One
U, V and W together can complete a work in 15 days. U alone can complete the work in 60 days. In how many days V and W together can complete the same work?
A10B20C14D12
Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View SolutionA alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View SolutionA and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View Solution