Doubtnut Promotions Sticky

In how many days will B alone complete the work?
I. A and B together can complete the work in 8 days. II. B and C together can complete the work in 10 days.
III. A and C together can complete the work in 12 days

A

Only I and II

B

Only II and II

C

I, II and III

D

Data is insufficient

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To determine how many days B alone will take to complete the work, we can analyze the information given in the statements step by step.

Step 1: Understand the Work Rates
Let's denote:
- The total work as 1 unit.
- The rate of work done by A as A (units of work per day).
- The rate of work done by B as B (units of work per day).
- The rate of work done by C as C (units of work per day).

Step 2: Analyze Statement I
From Statement I, we know:
- A and B together can complete the work in 8 days.
- Therefore, their combined work rate is:
A+B=18 (units of work per day)

Step 3: Analyze Statement II
From Statement II, we know:
- B and C together can complete the work in 10 days.
- Therefore, their combined work rate is:
B+C=110 (units of work per day)

Step 4: Analyze Statement III
From Statement III, we know:
- A and C together can complete the work in 12 days.
- Therefore, their combined work rate is:
A+C=112 (units of work per day)

Step 5: Set Up the Equations
Now we have three equations:
1. A+B=18
2. B+C=110
3. A+C=112

Step 6: Solve the Equations
To find the individual work rates, we can manipulate these equations.

- From equations (1) and (2), we can express A and C in terms of B:
- From (1): A=18B
- From (2): C=110B

Substituting these into equation (3):
(18B)+(110B)=112

Step 7: Combine and Solve
Combining the left side:
18+1102B=112

Finding a common denominator (which is 120):
15120+121202B=10120
271202B=10120

Rearranging gives:
2B=2712010120=17120
B=17240

Step 8: Calculate Days for B Alone
To find the number of days B alone will take to complete the work:
Days for B=1B=117240=2401714.12 days

Thus, B alone will complete the work in approximately 14.12 days.

Conclusion
The answer is that B alone will complete the work in approximately 14.12 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?

    A40
    B72
    C84
    D90
  • Question 2 - Select One

    P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?

    A1800
    B900
    C1200
    D1500
  • Question 3 - Select One

    U, V and W together can complete a work in 15 days. U alone can complete the work in 60 days. In how many days V and W together can complete the same work?

    A10
    B20
    C14
    D12