A and B together can do a work in 12 days. B and C together do it in 15 days. If A's efficiency is twice that of C, then the days required for B alone to finish the work is
60
30
20
15
The correct Answer is:C
To solve the problem step by step, let's define the efficiencies of A, B, and C and use the information given in the question.
Step 1: Define the efficiencies
Let the efficiency of C be c. Since A's efficiency is twice that of C, we have:
- Efficiency of A = 2c
- Efficiency of B = b
Step 2: Set up the equations based on the work done
From the problem, we know:
1. A and B together can complete the work in 12 days.
2. B and C together can complete the work in 15 days.
The work done in one day by A and B together is:
112 (work/day)
So, we can write:
2c+b=112(Equation 1)
The work done in one day by B and C together is:
115 (work/day)
So, we can write:
b+c=115(Equation 2)
Step 3: Solve the equations
Now we have two equations:
1. 2c+b=112
2. b+c=115
From Equation 2, we can express b in terms of c:
b=115−c(Equation 3)
Substituting Equation 3 into Equation 1:
2c+(115−c)=112
This simplifies to:
2c−c+115=112
c+115=112
Step 4: Isolate c
Now, we need to isolate c:
c=112−115
Finding a common denominator (which is 60):
c=560−460=160
Step 5: Find b
Now that we have c, we can find b using Equation 3:
b=115−c=115−160
Finding a common denominator (which is 60):
b=460−160=360=120
Step 6: Calculate the days required for B alone to finish the work
Since b represents the work done by B in one day, we can find the time taken by B to complete the entire work:
Days required by B=1b=1120=20 days
Final Answer
Thus, the days required for B alone to finish the work is 20 days.
---
Let the efficiency of C be c. Since A's efficiency is twice that of C, we have:
- Efficiency of A = 2c
- Efficiency of B = b
From the problem, we know:
1. A and B together can complete the work in 12 days.
2. B and C together can complete the work in 15 days.
112 (work/day)
So, we can write:
2c+b=112(Equation 1)
115 (work/day)
So, we can write:
b+c=115(Equation 2)
Now we have two equations:
1. 2c+b=112
2. b+c=115
b=115−c(Equation 3)
2c+(115−c)=112
This simplifies to:
2c−c+115=112
c+115=112
Now, we need to isolate c:
c=112−115
c=560−460=160
Now that we have c, we can find b using Equation 3:
b=115−c=115−160
Finding a common denominator (which is 60):
b=460−160=360=120
Since b represents the work done by B in one day, we can find the time taken by B to complete the entire work:
Days required by B=1b=1120=20 days
Thus, the days required for B alone to finish the work is 20 days.
Similar Questions
A and B can do a piece of work in 12 days. B and C together can do it in 15 days. If A is twice as good a workman as C, find in what time B alone can do it.
View SolutionA and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can do a work in 30 days and A alone can do it in 40 days. In how many days B alone can do this?
A120 daysB110 daysC80 daysD100 days - Question 2 - Select One
A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:
A12 daysB315 daysC16 daysD9313 days - Question 3 - Select One
A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
A48 daysB24 daysC16 daysD12 days
A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगेView SolutionA and B can do a work in 8 days and A alone can do it in 12 days. In how many days can B alone do it?
View Solution