Doubtnut Promotions Sticky

A and B together can do a work in 12 days. B and C together do it in 15 days. If A's efficiency is twice that of C, then the days required for B alone to finish the work is

A

60

B

30

C

20

D

15

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's define the efficiencies of A, B, and C and use the information given in the question.

Step 1: Define the efficiencies
Let the efficiency of C be c. Since A's efficiency is twice that of C, we have:
- Efficiency of A = 2c
- Efficiency of B = b

Step 2: Set up the equations based on the work done
From the problem, we know:
1. A and B together can complete the work in 12 days.
2. B and C together can complete the work in 15 days.

The work done in one day by A and B together is:
112 (work/day)
So, we can write:
2c+b=112(Equation 1)

The work done in one day by B and C together is:
115 (work/day)
So, we can write:
b+c=115(Equation 2)

Step 3: Solve the equations
Now we have two equations:
1. 2c+b=112
2. b+c=115

From Equation 2, we can express b in terms of c:
b=115c(Equation 3)

Substituting Equation 3 into Equation 1:
2c+(115c)=112
This simplifies to:
2cc+115=112
c+115=112

Step 4: Isolate c
Now, we need to isolate c:
c=112115

Finding a common denominator (which is 60):
c=560460=160

Step 5: Find b
Now that we have c, we can find b using Equation 3:
b=115c=115160
Finding a common denominator (which is 60):
b=460160=360=120

Step 6: Calculate the days required for B alone to finish the work
Since b represents the work done by B in one day, we can find the time taken by B to complete the entire work:
Days required by B=1b=1120=20 days

Final Answer
Thus, the days required for B alone to finish the work is 20 days.

---

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can do a work in 30 days and A alone can do it in 40 days. In how many days B alone can do this?

    A120 days
    B110 days
    C80 days
    D100 days
  • Question 2 - Select One

    A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:

    A12 days
    B315 days
    C16 days
    D9313 days
  • Question 3 - Select One

    A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

    A48 days
    B24 days
    C16 days
    D12 days