A and B do (35) th part of a work and the rest of the work is completed by C. If A, B and C take the same work for Rs. 5000, then what is the share fo C (in Rs.)?
3000
2500
2000
1500
The correct Answer is:C
To solve the problem step by step, we can follow these instructions:
Step 1: Understand the total work and the contributions of A, B, and C
A and B together complete 35 of the work, and C completes the remaining work.
Step 2: Calculate the work done by C
Since A and B complete 35 of the work, the fraction of work completed by C is:
1−35=25
This means C completes 25 of the total work.
Step 3: Determine the total payment for the work
The total payment for the work done by A, B, and C is Rs. 5000.
Step 4: Calculate the share of A and B
Since A and B together completed 35 of the work, their share of the payment can be calculated as follows:
Share of A and B=Total Payment×35=5000×35
Calculating this gives:
5000×35=5000×0.6=3000
So, A and B together receive Rs. 3000.
Step 5: Calculate the share of C
To find C's share, we subtract the amount received by A and B from the total payment:
Share of C=Total Payment−Share of A and B=5000−3000
Calculating this gives:
5000−3000=2000
Thus, C's share is Rs. 2000.
Final Answer
The share of C is Rs. 2000.
---
A and B together complete 35 of the work, and C completes the remaining work.
Since A and B complete 35 of the work, the fraction of work completed by C is:
1−35=25
This means C completes 25 of the total work.
The total payment for the work done by A, B, and C is Rs. 5000.
Since A and B together completed 35 of the work, their share of the payment can be calculated as follows:
Share of A and B=Total Payment×35=5000×35
Calculating this gives:
5000×35=5000×0.6=3000
So, A and B together receive Rs. 3000.
To find C's share, we subtract the amount received by A and B from the total payment:
Share of C=Total Payment−Share of A and B=5000−3000
Calculating this gives:
5000−3000=2000
Thus, C's share is Rs. 2000.
The share of C is Rs. 2000.
Similar Questions
A does 45 part of the work in 20 days and rest of the work is done by A and B in 3 days. In what time can B do the whole work.
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View Solution
Knowledge Check
- Question 1 - Select One
Sandy and Mandy do (813) th part of a work and the rest of the work was completed by Andy. If Sandy, Mandy and Andy take the same work for Rs. 2600, then what is the share (in Rs.) of Andy?
A1600B1400C800D1000 - Question 2 - Select One
Sandy and Mandy do (813)th part of a work and the rest of the work was completed by Andy. If Sandy, Mandy and Andy take the same work for Rs. 2600. then what is the share (in Rs.) of Andy?
A1600B1400C800D1000 - Question 3 - Select One
A can do a work in 8 days , B can do the same work in 10 days and C can do the same work in 12 days . If all three of them do the same work together and they are paid Rs. 7400, what is the share (in Rs.) of B ?
A2600B3000C2400D2000
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA and B together complete a work in 20 days. B alone can complete the same work in 60 days. They took Rs 36000 to complete the work. What will be the share of A (in Rs)?
View SolutionA and B together complete a work in 20 days. B alone can complete the same work in 60 days. They took Rs 36000 to complete the work. What will be the share of A (in Rs)?
View SolutionRashika can do a work in 5 days. Rashmi can do the same work in 7 days. Both of them finish the work together and they get Rs. 240 for the work. What is the share (in Rs.) of Rashika?
View SolutionP,Q and R undertook a work for Rs. 52000 . Together P and Q complete (2/5)th part of the work. What is the share (in Rs) of R?
View Solution