Doubtnut Promotions Sticky

In order to sat up standard target of performance for workers, it was necessary for Shiv Ltd. To fix standard time for workers to performs a particular job. For this Mr. Ganesh, the Production Manager of the company observed the workers when they were performing the job. He used a stopwatch in hand and noted down the averge time taken by workers for completion of the job. He repeated the same observation for 100 times and then calculated average time for the performance of the job. This was fixed as the standard time on the basis of which efficient and inefficient workers were distinguished.
Identify the technique of scientific management followed by Mr. Ganesh.

Video Solution
Text Solution
Verified by Experts

Time Study

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    The workers expected to finish the job.

    AThe job was expecting to being finished by the workers.
    BIt was expected that the workers would be finishing the job.
    CThe job was expected to been finished by the workers.
    DIt was expected by the workers that they would finish the job.
  • Question 2 - Select One

    If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.

    A125 days
    B122 days
    C120 days
    D116 days
  • Question 3 - Select One

    He is the poorest of the two workers.

    Athe poorer of
    Bthe poorest between
    Cpoorest of
    DNo Improvement