If 1 man or 2 women or 3 boys can do a piece of work in 44 days, then the same piece of work will be done by 1 man , 1 woman and 1 boy in
21 days
24 days
26 days
33 days
The correct Answer is:B
To solve the problem, we need to determine how long it will take for 1 man, 1 woman, and 1 boy to complete a piece of work together, given that 1 man or 2 women or 3 boys can complete the work in 44 days.
1. Determine the work done by each individual:
- Let the total work be represented as 1 unit.
- If 1 man can complete the work in 44 days, then the work done by 1 man in 1 day is:
Work done by 1 man in 1 day=144
- If 2 women can complete the work in 44 days, then the work done by 1 woman in 1 day is:
Work done by 1 woman in 1 day=12×44=188
- If 3 boys can complete the work in 44 days, then the work done by 1 boy in 1 day is:
Work done by 1 boy in 1 day=13×44=1132
2. Calculate the combined work done by 1 man, 1 woman, and 1 boy in 1 day:
- The total work done by 1 man, 1 woman, and 1 boy in 1 day is:
Total work in 1 day=144+188+1132
3. Find a common denominator to add the fractions:
- The least common multiple (LCM) of 44, 88, and 132 is 264.
- Convert each fraction:
144=6264,188=3264,1132=2264
- Now, add them:
Total work in 1 day=6264+3264+2264=11264
4. Determine how many days it will take to complete the work:
- If they can do 11264 of the work in 1 day, the total time X to complete 1 unit of work is:
X=111264=26411=24 days
Final Answer:
Thus, 1 man, 1 woman, and 1 boy together can complete the work in 24 days.
---
- Let the total work be represented as 1 unit.
- If 1 man can complete the work in 44 days, then the work done by 1 man in 1 day is:
Work done by 1 man in 1 day=144
Work done by 1 woman in 1 day=12×44=188
Work done by 1 boy in 1 day=13×44=1132
- The total work done by 1 man, 1 woman, and 1 boy in 1 day is:
Total work in 1 day=144+188+1132
- The least common multiple (LCM) of 44, 88, and 132 is 264.
- Convert each fraction:
144=6264,188=3264,1132=2264
- Now, add them:
Total work in 1 day=6264+3264+2264=11264
- If they can do 11264 of the work in 1 day, the total time X to complete 1 unit of work is:
X=111264=26411=24 days
Thus, 1 man, 1 woman, and 1 boy together can complete the work in 24 days.
Similar Questions
If 2 men and 7 boys do a piece of work in 14 days while 3 men and 8 boys do the same piece of work in 11 days, then in how many days will 8 men and 6 boys do thrice of that work?
(A) 11
(B) 21
(C) 31
(D) 41View SolutionIf one man or three women of five boys can do a piece of
work in 46 days then how many days will one man, one
woman and one boy together take to complete the same
piece of work?View Solution
Knowledge Check
- Question 1 - Select One
If 1 man or 2 women or 3 boys can do a piece of work in 44 days, then the same piece of work will be done by 1 man, 1 woman and 1 boy in
A21 daysB24 daysC26 daysD33 days - Question 2 - Select One
If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of work will be done by 1 man, 1 woman and 1 boy in :
A48 daysB36 daysC45 daysDnone of these - Question 3 - Select One
If one man or two women or three boys can do a piece of work in 22 days, then the same piece of work will be done by 1 man, 1 boy and 1 women in
A8 daysB12 daysC6 daysD11 days
If 1 man or 2 women or 3 boys can complete a piece of work in 88 days, then 1 man 1 women and 1 boy together will complete it in
View Solution1 man or 2 women or 3 boys can do a work in 44 days. Then, in how many days will 1 man, 1 woman and 1 boy do the work?
View SolutionIf 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in
View SolutionIf 1 man or 2 women or 3 boys can complete a piece of work in 88 days, then 1 man 1 women and 1 boy together will complete it in
View SolutionIf one man or two women or three boys can finish a work in 88 days, then how many days will one man, one woman and one boy together take to finish the same work?
View Solution