Doubtnut Promotions Sticky

Quantity I: A and B together can do a pices of work in 4 days. If A alone can do the same work in 6 days, then B alone can do the same work in?
Quantity II: A can do a pices of work in 4 hours, B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it ?

A

Quantity I> Quantity II

B

Quantity I Quantity II

C

Quantity II> Quantity II

D

Quantity II Quantity I

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we will analyze both quantities step by step.

Quantity I:
1. Understanding the Work Rates:
- Let the total work be represented as 1 unit of work.
- A and B together can complete the work in 4 days. Therefore, their combined work rate is:
Work rate of A and B=1 unit4 days=14 units/day

2. A's Work Rate:
- A alone can complete the work in 6 days. Therefore, A's work rate is:
Work rate of A=1 unit6 days=16 units/day

3. Finding B's Work Rate:
- Let B's work rate be b units/day. From the combined work rate, we have:
14=16+b
- Rearranging gives:
b=1416
- To subtract these fractions, find a common denominator (which is 12):
b=312212=112 units/day

4. Calculating Time for B Alone:
- If B's work rate is 112 units/day, then the time taken by B to complete the work alone is:
Time for B=1 unit112 units/day=12 days

Quantity II:
1. Understanding the Work Rates:
- A can do the work in 4 hours. Therefore, A's work rate is:
Work rate of A=1 unit4 hours=14 units/hour

2. B and C Together:
- B and C together can do the work in 3 hours. Therefore, their combined work rate is:
Work rate of B and C=1 unit3 hours=13 units/hour

3. A and C Together:
- A and C together can do the work in 2 hours. Therefore, their combined work rate is:
Work rate of A and C=1 unit2 hours=12 units/hour

4. Setting Up the Equations:
- Let B's work rate be b units/hour and C's work rate be c units/hour.
- From the equations, we have:
1. 14+c=12 (from A and C)
2. b+c=13 (from B and C)

5. Solving for C:
- From the first equation:
c=1214=14 units/hour

6. Finding B's Work Rate:
- Substitute c into the second equation:
b+14=13
- Rearranging gives:
b=1314
- Finding a common denominator (which is 12):
b=412312=112 units/hour

7. Calculating Time for B Alone:
- If B's work rate is 112 units/hour, then the time taken by B to complete the work alone is:
Time for B=1 unit112 units/hour=12 hours

Conclusion:
- Quantity I: B alone takes 12 days.
- Quantity II: B alone takes 12 hours.

Comparison:
- 12 days (Quantity I) is greater than 12 hours (Quantity II).

Final Answer:
- Quantity I is greater than Quantity II.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?

    A8 days
    B12 days
    C10 days
    D16 days
  • Question 2 - Select One

    A and B together can do a piece of work in 4 days and A alone can do it in 6 days, B alone can do the same work in :

    A1313 days
    B12 days
    C16 days
    D11 days
  • Question 3 - Select One

    A and B together can do a piece of work in 5 days and A alone can do it in 8 days. B alone can do the same piece of work in:

    A1113 days
    B1313 days
    C1645 days
    D1235 days