4 men & 18 women can do a piece of work in 2.5 days, then in how many days 12 woment can complete the same piece of work ?
A. Ratio of efficiency of men to woment is 3:2.
B. 6 men & 6 women can complete the dame work in 4 days.
Statement A alone is sufficient to answer the question but statement B alone is not sufficient to answer the questions.
Statement B alone is sufficient to answer the question but statement A alone is not sufficient to answer the question.
Both the statements taken together are necessary to answer the questions, but neither of the statements alone is sufficient to answer the question.
Either stetement A or stetement B by itself is sufficient to answer the question.
To solve the problem, we need to determine how many days 12 women can complete the same piece of work that 4 men and 18 women can do in 2.5 days. We will analyze the information given in both statements A and B to find the solution.
1. Understanding the Work Done by 4 Men and 18 Women:
- The total work done by 4 men and 18 women in 2.5 days can be expressed as:
Work=Number of Workers×Efficiency×Time
- Let the efficiency of one man be m and the efficiency of one woman be w.
- Therefore, the total work done can be written as:
Total Work=(4m+18w)×2.5
2. Using Statement A:
- Statement A gives the ratio of efficiency of men to women as 3:2. This means:
mw=32⟹m=32w
- Substituting m in the work equation:
Total Work=(4⋅32w+18w)×2.5
- Simplifying this:
=(6w+18w)×2.5=24w×2.5=60w
3. Finding the Work Done by 12 Women:
- The work done by 12 women in one day is 12w.
- To find the number of days d taken by 12 women to complete the total work:
60w=12w×d⟹d=60w12w=5 days
4. Using Statement B:
- Statement B states that 6 men and 6 women can complete the same work in 4 days.
- The total work done can be expressed as:
Total Work=(6m+6w)×4
- Substituting m=32w:
=(6⋅32w+6w)×4=(9w+6w)×4=15w×4=60w
- This confirms that the total work is consistent with the previous calculation.
5. Conclusion:
- From both statements A and B, we have determined that 12 women can complete the work in 5 days.
- Therefore, either statement A or statement B alone is sufficient to answer the question.
Final Answer:
12 women can complete the same piece of work in 5 days.
- The total work done by 4 men and 18 women in 2.5 days can be expressed as:
Work=Number of Workers×Efficiency×Time
- Let the efficiency of one man be m and the efficiency of one woman be w.
- Therefore, the total work done can be written as:
Total Work=(4m+18w)×2.5
- Statement A gives the ratio of efficiency of men to women as 3:2. This means:
mw=32⟹m=32w
- Substituting m in the work equation:
Total Work=(4⋅32w+18w)×2.5
- Simplifying this:
=(6w+18w)×2.5=24w×2.5=60w
- The work done by 12 women in one day is 12w.
- To find the number of days d taken by 12 women to complete the total work:
60w=12w×d⟹d=60w12w=5 days
- Statement B states that 6 men and 6 women can complete the same work in 4 days.
- The total work done can be expressed as:
Total Work=(6m+6w)×4
- Substituting m=32w:
=(6⋅32w+6w)×4=(9w+6w)×4=15w×4=60w
- This confirms that the total work is consistent with the previous calculation.
- From both statements A and B, we have determined that 12 women can complete the work in 5 days.
- Therefore, either statement A or statement B alone is sufficient to answer the question.
12 women can complete the same piece of work in 5 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
A4 daysB5 daysC3 daysD2 days21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
A6daysB5daysC4daysD7daysIf 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
A4 daysB5 daysC3 daysD2 days
If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View Solution12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
View SolutionIf 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days
View SolutionIf 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days
View SolutionIf 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days
View Solution