8 men can finish a piece
of work in 40 days. If 2 more men join them, the work will be computed in
(a) 30 days
(b) 32 days
(c) 36 days
(d) 25 days
To solve the problem step by step, we will use the concept of inverse variation, as the number of men and the number of days to complete the work are inversely related.
Step 1: Understand the Given Information
We know that:
- 8 men can finish the work in 40 days.
Step 2: Calculate the Total Work
We can calculate the total work in terms of "man-days":
- Total work = Number of men × Number of days
- Total work = 8 men × 40 days = 320 man-days.
Step 3: Determine the New Number of Men
If 2 more men join the original 8 men:
- New number of men = 8 + 2 = 10 men.
Step 4: Set Up the Equation
Let the number of days required to complete the work with 10 men be x.
Using the inverse variation relationship:
- Total work = Number of men × Number of days
- Therefore, we have:
10 men×x days=320 man-days
Step 5: Solve for x
Now we can solve for x:
10x=320
To isolate x, divide both sides by 10:
x=32010=32 days
Step 6: Conclusion
The work will be completed in 32 days when 2 more men join the original 8 men.
Final Answer
The correct option is (b) 32 days.
---
We know that:
- 8 men can finish the work in 40 days.
We can calculate the total work in terms of "man-days":
- Total work = Number of men × Number of days
- Total work = 8 men × 40 days = 320 man-days.
If 2 more men join the original 8 men:
- New number of men = 8 + 2 = 10 men.
Let the number of days required to complete the work with 10 men be x.
Using the inverse variation relationship:
- Total work = Number of men × Number of days
- Therefore, we have:
10 men×x days=320 man-days
Now we can solve for x:
10x=320
To isolate x, divide both sides by 10:
x=32010=32 days
The work will be completed in 32 days when 2 more men join the original 8 men.
The correct option is (b) 32 days.
Topper's Solved these Questions
Similar Questions
36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?
View Solution12 men can finish a piece of work in 25 days. The number of days in which the same piece of work can be done by 20 men, is
(a) 10 days
(b) 12 days
(c) 15 days
(d) 14 daysView Solution72 men do a piece of work in 25 days. In how many days will 30 men do the same work ?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View SolutionIf six men can do a piece of work in 6 days, then 3 men can do same work in
(a) 10 days
(b) 12 days
(c) 15 days
(d) 18 daysView SolutionMenstrual cycle is generally of
(a) 21 days
(b) 28 days
(c) 38 days
(d) 40 daysView SolutionIf 56 men can do a piece of work in 42 days. How many men will do it in 14 days?
View SolutionIf 52 men can do a piece of work in 35 days in how many days 28 men will do it ?
View SolutionIf 78 men can do a work in 140 days, in how many days will 42 men do the same work ?
View SolutionIf 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View Solution