Suneeta can embroider a saree in 15 days. Her sister-in-law Abha can do the job in 10 days. They start embroidering the saree together, but two days later Abha gives up the work and goes to her parents. In how many days will Suneeta finish the remaining work of embroidering the saree?
To solve the problem step by step, we will calculate the work done by Suneeta and Abha, and then determine how long it will take Suneeta to finish the remaining work after Abha leaves.
Step 1: Calculate Suneeta's work rate
Suneeta can complete the work in 15 days. Therefore, her work rate is:
Suneeta's work rate=115 (saree per day)
Step 2: Calculate Abha's work rate
Abha can complete the work in 10 days. Therefore, her work rate is:
Abha's work rate=110 (saree per day)
Step 3: Calculate their combined work rate
When Suneeta and Abha work together, their combined work rate is:
Combined work rate=115+110
To add these fractions, we need a common denominator. The least common multiple (LCM) of 15 and 10 is 30. Thus, we convert the fractions:
115=230,110=330
Now, adding the two:
Combined work rate=230+330=530=16 (saree per day)
Step 4: Calculate work done in the first 2 days
In 2 days, the amount of work they can complete together is:
Work done in 2 days=2×16=26=13 (saree)
Step 5: Calculate the remaining work
The total work is considered as 1 saree. Therefore, the remaining work after 2 days is:
Remaining work=1−13=23 (saree)
Step 6: Calculate the time taken by Suneeta to finish the remaining work
Now, we need to find out how long it will take Suneeta to complete the remaining 23 of the saree. Let x be the number of days Suneeta takes to finish the remaining work. We can set up the equation:
Work done by Suneeta in x days=115×x=23
To find x, we rearrange the equation:
x=23×15=10
Final Answer
Suneeta will finish the remaining work in 10 days after Abha leaves.
---
Suneeta can complete the work in 15 days. Therefore, her work rate is:
Suneeta's work rate=115 (saree per day)
Abha can complete the work in 10 days. Therefore, her work rate is:
Abha's work rate=110 (saree per day)
When Suneeta and Abha work together, their combined work rate is:
Combined work rate=115+110
To add these fractions, we need a common denominator. The least common multiple (LCM) of 15 and 10 is 30. Thus, we convert the fractions:
115=230,110=330
Now, adding the two:
Combined work rate=230+330=530=16 (saree per day)
In 2 days, the amount of work they can complete together is:
Work done in 2 days=2×16=26=13 (saree)
The total work is considered as 1 saree. Therefore, the remaining work after 2 days is:
Remaining work=1−13=23 (saree)
Now, we need to find out how long it will take Suneeta to complete the remaining 23 of the saree. Let x be the number of days Suneeta takes to finish the remaining work. We can set up the equation:
Work done by Suneeta in x days=115×x=23
To find x, we rearrange the equation:
x=23×15=10
Suneeta will finish the remaining work in 10 days after Abha leaves.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work?
View SolutionA can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work ?
View SolutionA and B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?
View SolutionA can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View SolutionA can do a piece of work in 80 days and B in 100 days. They work together for first 20 days before B goes away. In how many days will A manage to finish the remaining work?
View SolutionIf 78 men can do a work in 140 days, in how many days will 42 men do the same work ?
View SolutionA can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work ?
View SolutionA can do a work in 15 days and B in 20 days. If they work together on it for 4 days, what fraction of the work will be left ?
View SolutionA and B can do a piece of work in 45 days and 40 days respectively.They began the work together but A leaves after some days and B finishes the remaining work in 23 days. After how many days did A leave the work ?
View SolutionA takes 9 days more than B to do a certain piece of work. Together they can do the work in 6 days. How many days will A alone take to do the work?
View Solution