A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?
30 days
50 days
40 days
60 days
To solve the problem step by step, we need to determine how long C would take to complete the work alone. Here’s how we can break it down:
Step 1: Determine the work done by A and B in one day
- A can complete the work in 10 days, so A's work rate is:
Work rate of A=110 of the work per day
- B can complete the work in 12 days, so B's work rate is:
Work rate of B=112 of the work per day
Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B working together is:
Combined work rate=110+112
- To add these fractions, find a common denominator (which is 60):
110=660,112=560
- Therefore,
Combined work rate=660+560=1160 of the work per day
Step 3: Calculate the work done by A and B in 3 days
- In 3 days, the amount of work done by A and B together is:
Work done in 3 days=3×1160=3360=1120 of the work
Step 4: Determine the remaining work
- The total work is considered as 1 (or 60 units). The remaining work after 3 days is:
Remaining work=1−1120=920 of the work
Step 5: Calculate the work done by A alone in the next 2 days
- A continues to work alone for 2 days. The work done by A in 2 days is:
Work done by A in 2 days=2×110=210=15 of the work
Step 6: Determine the remaining work after A's contribution
- The remaining work after A works for 2 days is:
Remaining work=920−15
- Convert 15 to a fraction with a denominator of 20:
15=420
- Thus,
Remaining work=920−420=520=14 of the work
Step 7: Calculate the work done by C and A together in the last 2 days
- C joins A, and together they complete the remaining 14 of the work in 2 days. Therefore, their combined work rate is:
Combined work rate of A and C=110+C's work rate
- Let C's work rate be x. In 2 days, they complete 14 of the work:
2(110+x)=14
- Simplifying gives:
110+x=18
- Convert 110 to a fraction with a denominator of 40:
110=440,18=540
- Therefore:
x=540−440=140
Step 8: Determine how long C would take to complete the work alone
- If C can do 140 of the work in one day, then C would take:
Days taken by C=1140=40 days
Thus, C can complete the work alone in 40 days.
- A can complete the work in 10 days, so A's work rate is:
Work rate of A=110 of the work per day
- B can complete the work in 12 days, so B's work rate is:
Work rate of B=112 of the work per day
- The combined work rate of A and B working together is:
Combined work rate=110+112
- To add these fractions, find a common denominator (which is 60):
110=660,112=560
- Therefore,
Combined work rate=660+560=1160 of the work per day
- In 3 days, the amount of work done by A and B together is:
Work done in 3 days=3×1160=3360=1120 of the work
- The total work is considered as 1 (or 60 units). The remaining work after 3 days is:
Remaining work=1−1120=920 of the work
- A continues to work alone for 2 days. The work done by A in 2 days is:
Work done by A in 2 days=2×110=210=15 of the work
- The remaining work after A works for 2 days is:
Remaining work=920−15
- Convert 15 to a fraction with a denominator of 20:
15=420
- Thus,
Remaining work=920−420=520=14 of the work
- C joins A, and together they complete the remaining 14 of the work in 2 days. Therefore, their combined work rate is:
Combined work rate of A and C=110+C's work rate
- Let C's work rate be x. In 2 days, they complete 14 of the work:
2(110+x)=14
- Simplifying gives:
110+x=18
- Convert 110 to a fraction with a denominator of 40:
110=440,18=540
- Therefore:
x=540−440=140
- If C can do 140 of the work in one day, then C would take:
Days taken by C=1140=40 days
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 120 days and B can do it in 150 days. The work together for 20 days. Then, B leave and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it, if he works alone?
View SolutionA can do a piece of work in 6 days and A alone can do it in 10 days.In how many days can B alone do it?.
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?
A230 daysB225 daysC240 daysD220 days - Question 2 - Select One
A can do a work in 20 days. A and B can do it in 12 days together. In how many days B can do it alone?
A25B20C30D15 - Question 3 - Select One
A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?
A7daysB712 daysC8 daysD812days
A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionA alone can do a piece of work in 10 days and B alone can do it in 15 days. In how many days will A and B together do the same work?
View SolutionA and B together can do a piece of work in 8 days. B alone can do it in 12 days. B alone works at it for 4 days. In how many more days after that could A alone complete it.
View SolutionA can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
View Solution