A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?

A

30 days

B

50 days

C

40 days

D

60 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we need to determine how long C would take to complete the work alone. Here’s how we can break it down:

Step 1: Determine the work done by A and B in one day
- A can complete the work in 10 days, so A's work rate is:
Work rate of A=110 of the work per day
- B can complete the work in 12 days, so B's work rate is:
Work rate of B=112 of the work per day

Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B working together is:
Combined work rate=110+112
- To add these fractions, find a common denominator (which is 60):
110=660,112=560
- Therefore,
Combined work rate=660+560=1160 of the work per day

Step 3: Calculate the work done by A and B in 3 days
- In 3 days, the amount of work done by A and B together is:
Work done in 3 days=3×1160=3360=1120 of the work

Step 4: Determine the remaining work
- The total work is considered as 1 (or 60 units). The remaining work after 3 days is:
Remaining work=11120=920 of the work

Step 5: Calculate the work done by A alone in the next 2 days
- A continues to work alone for 2 days. The work done by A in 2 days is:
Work done by A in 2 days=2×110=210=15 of the work

Step 6: Determine the remaining work after A's contribution
- The remaining work after A works for 2 days is:
Remaining work=92015
- Convert 15 to a fraction with a denominator of 20:
15=420
- Thus,
Remaining work=920420=520=14 of the work

Step 7: Calculate the work done by C and A together in the last 2 days
- C joins A, and together they complete the remaining 14 of the work in 2 days. Therefore, their combined work rate is:
Combined work rate of A and C=110+C's work rate
- Let C's work rate be x. In 2 days, they complete 14 of the work:
2(110+x)=14
- Simplifying gives:
110+x=18
- Convert 110 to a fraction with a denominator of 40:
110=440,18=540
- Therefore:
x=540440=140

Step 8: Determine how long C would take to complete the work alone
- If C can do 140 of the work in one day, then C would take:
Days taken by C=1140=40 days

Thus, C can complete the work alone in 40 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?

    A230 days
    B225 days
    C240 days
    D220 days
  • A can do a work in 20 days. A and B can do it in 12 days together. In how many days B can do it alone?

    A25
    B20
    C30
    D15
  • A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

    A7days
    B712 days
    C8 days
    D812days