A can do a piece of work in 10 days, B in 12 days and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days befor the work is finished. How long did the work last ?
The correct Answer is:7 days
To solve the problem step by step, we will first determine the efficiency of each worker, then calculate the total work done, and finally find out how long the work lasted.
Step 1: Determine the efficiency of A, B, and C
- A can complete the work in 10 days, so A's efficiency = 1/10 of the work per day.
- B can complete the work in 12 days, so B's efficiency = 1/12 of the work per day.
- C can complete the work in 15 days, so C's efficiency = 1/15 of the work per day.
Step 2: Find the least common multiple (LCM) of the days
To find a common measure for their efficiencies, we calculate the LCM of 10, 12, and 15.
- LCM(10, 12, 15) = 60
Step 3: Convert efficiencies to a common scale
Now we convert their efficiencies based on the LCM:
- A's efficiency = 60/10 = 6 units of work per day
- B's efficiency = 60/12 = 5 units of work per day
- C's efficiency = 60/15 = 4 units of work per day
Step 4: Calculate the total work
The total work can be calculated as:
Total work = Efficiency × Time = 60 units (as calculated from A's work).
Step 5: Calculate work done in the first 2 days
In the first 2 days, all three work together:
- Total efficiency of A, B, and C = 6 + 5 + 4 = 15 units/day
- Work done in 2 days = 2 × 15 = 30 units
Step 6: Remaining work after 2 days
Remaining work = Total work - Work done in 2 days = 60 - 30 = 30 units
Step 7: Determine the time taken by B and C
B leaves 3 days before the work is finished, which means we need to find out how long B and C worked together before B left.
Let T be the total time taken to finish the work. Since B leaves 3 days before the work is finished, B and C work together for (T - 3) days.
Step 8: Work done by B and C together
During the time B and C work together:
- Work done by B and C in (T - 3) days = (5 + 4) × (T - 3) = 9(T - 3) units
Step 9: Work done by C alone
After B leaves, C works alone for 3 days:
- Work done by C in 3 days = 4 × 3 = 12 units
Step 10: Set up the equation
Total work done = Work done by A + Work done by B and C + Work done by C alone:
30+9(T−3)+12=60
Step 11: Solve the equation
Expanding the equation:
30+9T−27+12=60
9T+15=60
9T=60−15
9T=45
T=5
Step 12: Calculate total time of work
Total time of work = Time A worked + Time B and C worked together + Time C worked alone
=2+(T−3)+3
=2+(5−3)+3
=2+2+3=7 days
Final Answer
The total duration of the work lasted 7 days.
---
- A can complete the work in 10 days, so A's efficiency = 1/10 of the work per day.
- B can complete the work in 12 days, so B's efficiency = 1/12 of the work per day.
- C can complete the work in 15 days, so C's efficiency = 1/15 of the work per day.
To find a common measure for their efficiencies, we calculate the LCM of 10, 12, and 15.
- LCM(10, 12, 15) = 60
Now we convert their efficiencies based on the LCM:
- A's efficiency = 60/10 = 6 units of work per day
- B's efficiency = 60/12 = 5 units of work per day
- C's efficiency = 60/15 = 4 units of work per day
The total work can be calculated as:
Total work = Efficiency × Time = 60 units (as calculated from A's work).
In the first 2 days, all three work together:
- Total efficiency of A, B, and C = 6 + 5 + 4 = 15 units/day
- Work done in 2 days = 2 × 15 = 30 units
Remaining work = Total work - Work done in 2 days = 60 - 30 = 30 units
B leaves 3 days before the work is finished, which means we need to find out how long B and C worked together before B left.
During the time B and C work together:
- Work done by B and C in (T - 3) days = (5 + 4) × (T - 3) = 9(T - 3) units
After B leaves, C works alone for 3 days:
- Work done by C in 3 days = 4 × 3 = 12 units
Total work done = Work done by A + Work done by B and C + Work done by C alone:
30+9(T−3)+12=60
Expanding the equation:
30+9T−27+12=60
9T+15=60
9T=60−15
9T=45
T=5
Total time of work = Time A worked + Time B and C worked together + Time C worked alone
=2+(T−3)+3
=2+(5−3)+3
=2+2+3=7 days
The total duration of the work lasted 7 days.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?
View SolutionA can do a piece of work in 10 days and B in 15 days. How long will they take to finish it working together ?
View SolutionIf 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View SolutionRakesh can do piece of work in 20 days. How much work can be do in 4 days?
View SolutionIf 12 women can do a piece of work in 9 days, in how many days can 18 women do it ?
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
How long will it take them to do the work, working together ?View SolutionA and B can do a piece of work in 18 days .B and C in 24 days and A and C in 36 days .In what time can they do it , all works together
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
In what time can each finish it working alone ?View SolutionA can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work?
View SolutionAnil can do a piece of work in 5 days and ankur in 4 days. How long will they take to do the same work, if they work together?
View Solution