Doubtnut Promotions Sticky

Gold worth about 3 crores was ______ by the customs at the airport while being smuggled.

A

conserved

B

preserved

C

sold

D

confiscated

Text Solution
Verified by Experts

The correct Answer is:D

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    Sentences are given with blanks to be filled in with an appropriate word (s)four alternative are suggested for each question choose the correct alternatives out of the four options
    A trader was______at the city airport early on Thursday for carrying gold jewellry worth over 1crore
    (a)hindered
    (b)detained
    (c)retained
    (d)blocked

    Ahindered
    Bdetained
    Cretained
    Dblocked
  • Question 2 - Select One

    The much-awaited expansion o f Delhi’s Indira Gandhi International Airport is expected to begin by March-end as the airport operator has received three b ids f or the R 9,000-crore project, two officials familiar with the matter said. Two bids are from foreign companies while one is from an Indian firm. The airport operator, the GMR Group-led Delhi International Airport Ltd (DIAL), is expected to finalise the bidder this week. After the announcement, the successful bidder is expected to take around two months to mobilise the workforce a nd begin expansion work. The bid document says the selected company has to complete work in 42 months. All the three bidders are reported to have quoted 39 months, the sources said. The expansion is aimed to meet the rapid traffic growth that has already made IGI Asia’s seventh busiest airport. The selected company will work on the expansion of Terminal 1 and Terminal 3 and the construction of a new runway and taxiways. Roads leading to the airport will be widened and new approach roads will be built. The operator expects the expansion, which will start with Terminal 1, to be completed by 2021 taking the overall handling capacity of the airport to 85 million passengers per year from the current 70 million. It will be followed by Phase 2 of the expansion, which includes construction of another brand new terminal. Data released last year by Airports Council International, the trade grouping of w orld airports, showed that Delhi, the country’s busiest airport by passenger traffic, grew 14.1% year on year to 63.45 million in 2017. It was the first time it breached the 60-million passenger mark. In 2018, it was just below the 70-million mark. The new air traffic control (ATC) tower, w hich will open in 2019, and the fourth runway, to be launched in 2021, would help it reduce air congestion and handle more flights. “Terminal 1 handles domestic traffic for low-cost carriers. These have registered a phenomenal growth in the last f ew years, calling for an expansion of the terminal. Delhi M etro under its Phase 3 programme is connecting this terminal to catchment areas of central and south Delhi. Since T 1 is operating beyond its capacity, the expansion will begin from there and cover the airside, terminal building and city s ide,” said a DIAL official According to the Master Plan, T1’s capacity will increase from 20 million to 40 million and that of Terminal 3 from 34 million to 45 million. Inter-terminal connectivity through the Airport Metro between T1 and T3 is also part of the expansion plan. DIAL has appointed AECOM, a design and development consultant for infrastructure projects, to complete the preliminary design for the expansion work.
    The expansion of the airport will begin from:

    AConstruction of a new terminal to handle the increasing load.
    BTerminal 3 which handles international traffic.
    CConstruction of a new runway and taxiways.
    DTerminal 1 which handles fast growing domestic traffic.
  • Question 3 - Select One

    Read the following passage and answer the questions given after it.
    The much-awaited expansion of Delhi.s Indira Gandhi International Airport is expected to begin by March-end as the airport operator has received three bids for the 9,000 crore project, two officials familiar with the matter said.
    Two bids are from foreign companies while one is from an Indian firm. The airport operator, the GMR Group-led Delhi International Airport Ltd (DIAL), is expected to finalise the bidder this week. After the announcement, the successful bidder is expected to take around two months to mobilise the workforce and begin expansion work,
    The bid document says the select company has to complete work in 42 months. All the three bidders are reported to have quoted 39 months, the sources said.
    The expansion is aimed to meet the rapid traffic growth that has already made IGI Asia.s seventh busiest airport. The selected company will work on the expansion of Terminal 1 and Terminal 3 and the construction of a new runway and taxiways, Roads leading to the airport will be widened and new approach roads will be built. The operator expects the expansion, which will start with Terminal 1, to be completed by 2021-taking the overall handling capacity of the airport to 85 million passengers per year from the current 70 million. It will be followed by Phase 2 of the expansion, which includes construction of another brand new terminal.
    Data released last year by Airports Council International showed that the passenger traffic at the Delhi Airport grew 14.1% year on year to 63-45 million in 2017. It was the first time it breached the 60 million passenger mark. In 2018, it was just below 70 million mark.
    The new air traffic control (ATC) tower, which will open in 2019, and the fourth runway, to be launched in 2021, would help it reduce air congestion and handle more flights.
    "Terminal 1 handles domestic traffic for low-cost carriers. These have registered a phenomenal growth in the last few years, calling for an expansion of the terminal. Delhi Metro under its Phase 3 programme is connecting this terminal to catchment areas of central and south Delhi. Since Ti is operating beyond its capacity, the expansion will begin from there and cover the airside, terminal building and city side," saida DIAL official.
    According to the Master Plan, Ti.s capacity will increase from 20 million to 40 million and that of Terminal 3 from 34 million to 45 million. Inter-terminal connectivity through the Airport Metro between T1 and T3 is also part of the expansion plan.
    DIAL has appointed AECOM, a design and development consultant for infrastructure projects, to complete the preliminary design for the expansion work.
    The expansion of the airport will begin from

    Aconstruction of a new terminal to handle the increasing load
    BTerminal 3 which handles international traffic
    Cconstruction of a new runway and taxiways
    DTerminal 1 which handles fast growing domestic traffic