A takes 6 hours less than B to complete a work. If together they complete the work in 13 hours 20 minutes, find how much time will B alone take to complete the work.
Let, B alone completes the work in x hours, then A alone will complete the work in (x-6) hours.
∵1x−6+1x=340 (13hr+20min=403hrs.)
⇒x+x−6(x−6)x=340
⇒3x2−18x=80x−240
⇒3x2−98x+240=0
⇒3x2−90x−8x+240=0
3x(x−30)−8(x−30)=0
⇒(x−30)(3x−8)=0
⇒x=30orx=83
⇒x=30 (ifx=83,then x-6 in negative) ∵ B alone will take 30 hours to complete the work.
Topper's Solved these Questions
- BOOK - NAGEEN PRAKASHAN ENGLISHCHAPTER - QUADRATIC EQUATIONSEXERCISE - Problems From NCERT /exemplar17videos
QUADRATIC EQUATIONS
- BOOK - NAGEEN PRAKASHAN ENGLISHCHAPTER - QUADRATIC EQUATIONSEXERCISE - Exercise 4a37videos
QUADRATIC EQUATIONS
- BOOK - NAGEEN PRAKASHAN ENGLISHCHAPTER - PROBABILITYEXERCISE - Revision Exercise Very Short Answer/short Answer Questions16videos
PROBABILITY
- BOOK - NAGEEN PRAKASHAN ENGLISHCHAPTER - REAL NUMBERSEXERCISE - Revision Exercise Long Answer Questions5videos
REAL NUMBERS
Similar Questions
B takes 16 days less than A to do a certain piece of work. If both working together can complete the work in 15 days, in how many days will B alone complete the work ?
View SolutionOne pipe can fill a cistren in 3 hours less than the other. The two pipes together can fill the cistern in 6 hours 40 minutes. Find the time that each pipe will take to fill the cistern.
View Solution
Knowledge Check
- Question 1 - Select One
A project manager estimates that a project will take x hours to complete, where x gt 100. The goal is for the estimate to be within 10 hours of the time it will actually take to complete the project. If the manager meets the goal and it takes y hours to complete the project, which of the following inequalities represents the relationship between the estimated time and the actual completion time?
Ax+y<10By>x+10Cy<x−10D−10<y−x<10 - Question 2 - Select One
A plumber works twice as fast as his apprentice. After the plumber has worked alone for 3 hours, his apprentice joins him and working together they complete the job 4 hours later. How many hours would it have taken the plumber to do the entire job by himself?
A9B12C14D18
A takes 9 days more than B to do a certain piece of work. Together they can do the work in 6 days. How many days will A alone take to do the work?
View Solution2 men or 3 women can do a piece of work in 45 days. Find, in how many days will 6 men and 1 woman be able to complete the same work ?
View Solution40% of a first order reaction is completed in 50 minutes. How much time will it take for the completion of 80% of this reaction?
View SolutionIf 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it ?
View SolutionA takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
View SolutionIn a zero order reaction , 20% of the reaction complete in 10 s. How much time it will take to complete 50% of the reaction ?
View Solution