240 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is
240 आदमी प्रतिदिन 5 घंटे काम करके एक काम को 20 दिन में पूरा कर सकते है। उसी काम को प्रतिदिन 8 घंटे काम करके 10 दिन के भीतर पूरा करने के लिए अपेक्षित आदमियों की न्यूनतम संख्या है-
310
300
313
312
To solve the problem, we need to determine the minimum number of men required to complete the work in a specified time and with a different working hour per day.
1. Understand the Given Information:
- 240 men can finish the work in 20 days working 5 hours a day.
- We need to find out how many men (let's denote this as P2) are required to finish the same work in 10 days working 8 hours a day.
2. Calculate the Total Work Done:
- The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days×Hours per Day
- For the first scenario:
Total Work=240 men×20 days×5 hours/day=240×20×5=24000 man-hours
3. Set Up the Equation for the New Scenario:
- In the new scenario, we want to finish the same total work (24000 man-hours) in 10 days working 8 hours a day:
Total Work=P2×10 days×8 hours/day
- This gives us the equation:
24000=P2×10×8
4. Solve for P2:
- Rearranging the equation to solve for P2:
P2=2400010×8=2400080=300
5. Conclusion:
- Therefore, the minimum number of men required to finish the work in 10 days working 8 hours a day is 300 men.
- 240 men can finish the work in 20 days working 5 hours a day.
- We need to find out how many men (let's denote this as P2) are required to finish the same work in 10 days working 8 hours a day.
- The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days×Hours per Day
- For the first scenario:
Total Work=240 men×20 days×5 hours/day=240×20×5=24000 man-hours
- In the new scenario, we want to finish the same total work (24000 man-hours) in 10 days working 8 hours a day:
Total Work=P2×10 days×8 hours/day
- This gives us the equation:
24000=P2×10×8
- Rearranging the equation to solve for P2:
P2=2400010×8=2400080=300
- Therefore, the minimum number of men required to finish the work in 10 days working 8 hours a day is 300 men.
Topper's Solved these Questions
Similar Questions
If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?
View Solution10 men can complete a work in 30 days by working for 8 hours per day. In how many days 12 men working 4 hours a day will complete the work?
किसी कार्य को 10 पुरुष प्रतिदिन 8 घंटों तक कार्य कर 30 दिनों में पूरा कर सकते हैं | 12 पुरुष प्रतिदिन 4 घंटे कार्य कर उसी कार्य को कितने दिनों में पूरा करेंगे?
View Solution
Knowledge Check
24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:
Aa. 30Bb. 32Cc. 34Dd. 36If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?
A52B31C13D65If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days
If Dev can make 40 chairs in 20 days, working 10 hours per day then in how many days can he make 10 chairs working 8 hours per day?
प्रतिदिन 10 घंटे काम करके यदि देव 20 दिनों में 40 कुर्सियाँ बना सकता है,तो प्रतिदिन 8 घंटे काम करके 10 कुर्सियाँ कितने दिन में बनाएगा ?
View SolutionIf 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?
View SolutionIf 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View SolutionShyam can complete a task in 12 days by working 10 hours a day. How many hours a day should he work to complete the task in 8 days?
श्याम एक दिन में 10 घंटे कार्य करके किसी कार्य को 12 दिनों में पूरा कर सकता है। इस कार्य को 8 दिनों में पूरा करने के लिए उसे प्रतिदिन कितने घंटे कार्य करना चाहिए?
View Solution