A, B and C can complete a piece of work in 4, 20 and 60 days respectively. Working together, they can complete the one third work in how many days ?
A, B और C किसी कार्य को क्रमशः 4, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे एक तिहाई कार्य कितने दिनों में समाप्त करेंगे ?

A

1319

B

1119

C

319

D

2119

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to determine how long A, B, and C will take to complete one-third of a piece of work when they work together.

1. Determine the Work Done by Each Person in One Day:
- A can complete the work in 4 days. Therefore, A's work per day = 14 of the work.
- B can complete the work in 20 days. Therefore, B's work per day = 120 of the work.
- C can complete the work in 60 days. Therefore, C's work per day = 160 of the work.

2. Calculate the Total Work Done by A, B, and C Together in One Day:
- Total work done in one day = A's work + B's work + C's work
- Total work done in one day = 14+120+160

3. Find a Common Denominator:
- The least common multiple (LCM) of 4, 20, and 60 is 60.
- Convert each fraction:
- 14=1560
- 120=360
- 160=160

4. Add the Fractions:
- Total work done in one day = 1560+360+160=1960

5. Determine the Total Work for One-Third of the Job:
- If we consider the total work to be 60 units (as it is divisible by 4, 20, and 60), then one-third of the work = 603=20 units.

6. Calculate the Time Taken to Complete One-Third of the Work:
- If they can do 1960 of the work in one day, we need to find out how many days it will take to complete 20 units.
- Let x be the number of days required to complete 20 units.
- The equation will be:
1960×x=20
- Solving for x:
x=20×6019=120019

7. Convert to Mixed Number:
- To convert 120019 into a mixed number:
- 1200 divided by 19 gives approximately 63 with a remainder.
- The remainder is 1200(63×19)=12001197=3.
- Thus, 120019=63319.

Final Answer:
The time taken by A, B, and C to complete one-third of the work together is 63319 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

    A11
    B12
    C13
    D14