A alone can do a piece of work in 30 days. B alone can do the same work in 40 days. If they work alternately (Alternate Days) starting from A, then in how many days (upto two decimal places) the work will be completed?
A अकेला किकसी कार्य को 30 दिन में कर सकता है | B अकेला उसी कार्य को 40 दिन में कर सकता है | यदि A से शुरुआत करके , वे बारी बारी काम करते हैं, तो कार्य कितने दिनों में पूरा हो जाएगा?

A

34.25

B

32.33

C

16.33

D

17.25

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem of how many days A and B will take to complete the work when they work alternately, we can follow these steps:

Step 1: Determine the work done by A and B in one day.
- A can complete the work in 30 days, so A's work in one day is:
Work done by A in one day=130

- B can complete the work in 40 days, so B's work in one day is:
Work done by B in one day=140

Step 2: Calculate the total work done in two days (one cycle of A and B working).
- In one cycle (2 days), A works on the first day and B works on the second day. Therefore, the total work done in two days is:
Total work in 2 days=Work done by A+Work done by B=130+140

Step 3: Find a common denominator and add the fractions.
- The least common multiple (LCM) of 30 and 40 is 120. We convert the fractions:
130=4120,140=3120
- Now add them:
Total work in 2 days=4120+3120=7120

Step 4: Calculate how many cycles are needed to complete the work.
- The total work is considered as 1 (the whole work). To find out how many cycles (2 days each) are needed to complete the work, we set up the equation:
Number of cycles=17120=120717.14 cycles

Step 5: Calculate the total number of days.
- Since each cycle takes 2 days, the total number of days for 17 complete cycles is:
Total days for 17 cycles=17×2=34 days

Step 6: Determine the remaining work after 34 days.
- In 34 days, the work done is:
Work done=17×7120=119120
- Remaining work is:
Remaining work=1119120=1120

Step 7: Determine who will work on the next day.
- On the 35th day, it will be A's turn to work. A can complete 130 of the work in one day, which is more than enough to finish the remaining 1120 of the work.

Step 8: Calculate the fraction of a day needed to finish the remaining work.
- The time taken by A to finish the remaining work is:
Time taken=Remaining workWork done by A in one day=1120130=1120×30=14 days

Step 9: Add the additional time to the total days.
- Therefore, the total time taken to complete the work is:
Total time=34+14=34.25 days

Final Answer
The work will be completed in 34.25 days.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together can do a work in 30 days and A alone can do it in 40 days. In how many days B alone can do this?

    A120 days
    B110 days
    C80 days
    D100 days