A alone can do a piece of work in 30 days. B alone can do the same work in 40 days. If they work alternately (Alternate Days) starting from A, then in how many days (upto two decimal places) the work will be completed?
A अकेला किकसी कार्य को 30 दिन में कर सकता है | B अकेला उसी कार्य को 40 दिन में कर सकता है | यदि A से शुरुआत करके , वे बारी बारी काम करते हैं, तो कार्य कितने दिनों में पूरा हो जाएगा?
34.25
32.33
16.33
17.25
To solve the problem of how many days A and B will take to complete the work when they work alternately, we can follow these steps:
Step 1: Determine the work done by A and B in one day.
- A can complete the work in 30 days, so A's work in one day is:
Work done by A in one day=130
- B can complete the work in 40 days, so B's work in one day is:
Work done by B in one day=140
Step 2: Calculate the total work done in two days (one cycle of A and B working).
- In one cycle (2 days), A works on the first day and B works on the second day. Therefore, the total work done in two days is:
Total work in 2 days=Work done by A+Work done by B=130+140
Step 3: Find a common denominator and add the fractions.
- The least common multiple (LCM) of 30 and 40 is 120. We convert the fractions:
130=4120,140=3120
- Now add them:
Total work in 2 days=4120+3120=7120
Step 4: Calculate how many cycles are needed to complete the work.
- The total work is considered as 1 (the whole work). To find out how many cycles (2 days each) are needed to complete the work, we set up the equation:
Number of cycles=17120=1207≈17.14 cycles
Step 5: Calculate the total number of days.
- Since each cycle takes 2 days, the total number of days for 17 complete cycles is:
Total days for 17 cycles=17×2=34 days
Step 6: Determine the remaining work after 34 days.
- In 34 days, the work done is:
Work done=17×7120=119120
- Remaining work is:
Remaining work=1−119120=1120
Step 7: Determine who will work on the next day.
- On the 35th day, it will be A's turn to work. A can complete 130 of the work in one day, which is more than enough to finish the remaining 1120 of the work.
Step 8: Calculate the fraction of a day needed to finish the remaining work.
- The time taken by A to finish the remaining work is:
Time taken=Remaining workWork done by A in one day=1120130=1120×30=14 days
Step 9: Add the additional time to the total days.
- Therefore, the total time taken to complete the work is:
Total time=34+14=34.25 days
Final Answer
The work will be completed in 34.25 days.
---
- A can complete the work in 30 days, so A's work in one day is:
Work done by A in one day=130
- B can complete the work in 40 days, so B's work in one day is:
Work done by B in one day=140
- In one cycle (2 days), A works on the first day and B works on the second day. Therefore, the total work done in two days is:
Total work in 2 days=Work done by A+Work done by B=130+140
- The least common multiple (LCM) of 30 and 40 is 120. We convert the fractions:
130=4120,140=3120
- Now add them:
Total work in 2 days=4120+3120=7120
- The total work is considered as 1 (the whole work). To find out how many cycles (2 days each) are needed to complete the work, we set up the equation:
Number of cycles=17120=1207≈17.14 cycles
- Since each cycle takes 2 days, the total number of days for 17 complete cycles is:
Total days for 17 cycles=17×2=34 days
- In 34 days, the work done is:
Work done=17×7120=119120
- Remaining work is:
Remaining work=1−119120=1120
- On the 35th day, it will be A's turn to work. A can complete 130 of the work in one day, which is more than enough to finish the remaining 1120 of the work.
- The time taken by A to finish the remaining work is:
Time taken=Remaining workWork done by A in one day=1120130=1120×30=14 days
- Therefore, the total time taken to complete the work is:
Total time=34+14=34.25 days
The work will be completed in 34.25 days.
Topper's Solved these Questions
Similar Questions
A alone can do a work in 30 days. B alone can do the same work in 60 days. If they work together for 5 days, then what part of the work will be left?
A किसी कार्य को अकेला 30 दिन में कर सकता है | B उसी कार्य को अकेला 60 दिन में कर सकता है | यदि वे 5 दिन तक एक साथ कार्य करते हैं, तो कार्य का कितना हिस्सा शेष रह जाएगा?
View SolutionSamrat alone can complete a work in 10 days and Virat alone can complete the same work in 40 days. If they are working on alternate days with Samrat starting the work, then in how many days will the total work be completed ?
सम्राट अकेले 10 दिनों में एक काम पूरा कर सकता है और विराट अकेले उसी काम को 40 दिनों में पूरा कर सकता है। सम्राट इस कार्य को आरम्भ करता है और फिर दोनों इसे बारी बारी से करते है, इस प्रकार यह कार्य कितने दिनों में समाप्त हो जाएगा ?
View Solution
Knowledge Check
A and B together can do a work in 30 days and A alone can do it in 40 days. In how many days B alone can do this?
A120 daysB110 daysC80 daysD100 days
A and B together can do a piece work in 20 days. B and C together can do the same work in 25 days. C and A together can do the same work in 15 days. In how many days A alone can do the work?
A तथा B मिलकर किसी कार्य को 20 दिन में कर सकते हैं | B तथा C मिलकर उसी कार्य को 25 दिन में कर सकते हैं | C तथा A मिलकर उसी कार्य को 15 दिन में कर सकते हैं | A अकेला उस कार्य को कितने दिनों में कर सकता है?
View SolutionA can do a piece of work alone in 10 days. B can do the same work in 15 days alone. They start the work together but B leaves the work 2 days after the start and A alone completes the remaining work. In how many days the work will be completed?
A किसी कार्य को अकेला 10 दिन में कर सकता है |B उसी कार्य को अकेला 15 दिन में कर सकता है | वे एक साथ मिलकर कार्य शुरू करते हैं परन्तु B कार्य आरंभ होने के 2 दिन बाद कार्य छोड़ देता है तथा A शेष कार्य को अकेला पूरा करता है | कार्य को पूरा होने में कुल कितने दिन लगेंगे?
View SolutionA can do a piece of work alone in 8 days. B can do the same work alone in 21 days. If they work together for 3 days, then how much work is completed?
A अकेले किसी कार्य को 8 दिनों में पूरा कर सकता है, B वही कार्य अकेले 21 दिनों में कर सकता है। यदि वे 3 दिनों के लिए एक साथ काम करते हैं, तो कितना काम पूरा होता है?
View SolutionA can do a work in 30 days, B can do the same work in 48 days. After working alone for 20 days A left and B started working, how long will B take to complete the work?
A किसी कार्य को 30 दिनों में कर सकता है,B इसी कार्य को 48 दिनों में कर सकता है | 20 दिन तक अकेले कार्य करने के बाद A ने छोड़ दिया तथा B ने कार्य करना शुरू कर दिया |B को इस कार्य को पूरा करने में कितना समय लगेगा ?
View SolutionA can complete a task in 18 days while B can complete the same task in 12 days. If both work together for 6 days, and then A leaves. In how many days will B complete the task?
A किसी कार्य को 18 दिनों में पूरा कर सकता है जबकि B उसी कार्य को 12 दिनों में पूरा कर सकता है। यदि दोनों 6 दिनों के लिए एक साथ कार्य करते हैं, और फिर A कार्य छोड़ देता है, तो B कार्य को कितने दिनों में पूरा करेगा?
View SolutionA and B can do a piece of work in 36 days, B and C can do the same work in 60 days. A and C can do the same work in 45 days. In how many days can A alone complete the work ?
A और B 36 दिनों में एक कार्य को कर सकते हैं, B और C 60 दिनों में उसी कार्य को कर सकते हैं। A और C उसी कार्य को 45 दिनों में कर सकते हैं। A अकेले कितने दिनों में वह कार्य पूरा कर सकता है?
View SolutionA and B can do a piece of work in 36 days, B and C can do the same work in 60 days. A and C can do the same work in 45 days. In how many days can B alone complete the same work?
A और B एक कार्य 36 दिनों में कर सकते हैं, B और C उसी कार्य को 60 दिनों में कर सकते हैं। A और C उसी कार्य को 45 दिनों में कर सकते हैं। B अकेले कितने दिनों में कार्य पूरा कर सकता है?
View Solution