B works three times more slowly than A and C together. C can do it twice slowly than A and B. if they work together, the work is completed in 10 days. In how many days they will do it separately?
24, 40, 30
40, 30, 24
40,24, 20
30, 20, 40
The correct Answer is:A
To solve the problem step by step, we will define the efficiencies of A, B, and C based on the information given and then calculate the time taken by each to complete the work separately.
Step 1: Define the relationship between A, B, and C
- Let the efficiency of A be a (units of work per day).
- According to the problem, B works three times more slowly than A and C together. Therefore, if A and C together can do a+c work, then B's efficiency can be expressed as:
b=13(a+c)
Step 2: Define C's efficiency
- The problem states that C works twice as slowly as A and B together. Therefore, if A and B together can do a+b work, then C's efficiency can be expressed as:
c=12(a+b)
Step 3: Express B's efficiency in terms of A and C
- From the equation for B, we can substitute c from the previous step:
b=13(a+12(a+b))
Simplifying this gives:
b=13(a+12a+12b)=13(32a+12b)
Multiplying through by 3 to eliminate the fraction:
3b=32a+12b
Rearranging gives:
52b=32a⟹b=35a
Step 4: Substitute B's efficiency back into C's equation
- Now substituting b back into C's equation:
c=12(a+35a)=12(85a)=45a
Step 5: Calculate total efficiency
- Now we have:
- a (efficiency of A)
- b=35a (efficiency of B)
- c=45a (efficiency of C)
- The total efficiency of A, B, and C together is:
a+b+c=a+35a+45a=a+75a=125a
Step 6: Work done in 10 days
- According to the problem, A, B, and C together complete the work in 10 days. Therefore, the total work done is:
Total Work=Total Efficiency×Time=125a×10=24a
Step 7: Calculate individual times
- Now we can find the time taken by each to complete the work separately:
- Time taken by A:
TimeA=Total WorkEfficiency of A=24aa=24 days
- Time taken by B:
TimeB=24a35a=24×53=40 days
- Time taken by C:
TimeC=24a45a=24×54=30 days
Final Answer
- Therefore, the time taken by A, B, and C to complete the work separately is:
- A: 24 days
- B: 40 days
- C: 30 days
- Let the efficiency of A be a (units of work per day).
- According to the problem, B works three times more slowly than A and C together. Therefore, if A and C together can do a+c work, then B's efficiency can be expressed as:
b=13(a+c)
- The problem states that C works twice as slowly as A and B together. Therefore, if A and B together can do a+b work, then C's efficiency can be expressed as:
c=12(a+b)
- From the equation for B, we can substitute c from the previous step:
b=13(a+12(a+b))
Simplifying this gives:
b=13(a+12a+12b)=13(32a+12b)
Multiplying through by 3 to eliminate the fraction:
3b=32a+12b
Rearranging gives:
52b=32a⟹b=35a
- Now substituting b back into C's equation:
c=12(a+35a)=12(85a)=45a
- Now we have:
- a (efficiency of A)
- b=35a (efficiency of B)
- c=45a (efficiency of C)
a+b+c=a+35a+45a=a+75a=125a
- According to the problem, A, B, and C together complete the work in 10 days. Therefore, the total work done is:
Total Work=Total Efficiency×Time=125a×10=24a
- Now we can find the time taken by each to complete the work separately:
- Time taken by A:
TimeA=Total WorkEfficiency of A=24aa=24 days
- Time taken by B:
TimeB=24a35a=24×53=40 days
- Time taken by C:
TimeC=24a45a=24×54=30 days
- Therefore, the time taken by A, B, and C to complete the work separately is:
- A: 24 days
- B: 40 days
- C: 30 days
Topper's Solved these Questions
Similar Questions
Knowledge Check
To do a certain work, B would take time thrice as long as A and C together and C twice as long as A and B together. The three men together complete the work in 10 days. The time taken by A to complete the work separately is
A22 daysB24 daysC30 daysD20 daysA can do a certain work in the same time as B and C together can do. If A and B together can do the work in 8 days and C alone can do the same work in 40 days, in how many days will Balone do the same work?
A25 daysB30 daysC20 daysD15 daysA and B together can finish a work in 15 days. A and C take 2 days more to complete the same work than that of B and C. AB and C together complete the work in 8 days. In how many days will A finish it separately?
A40 daysB24 daysC1717 daysD20 days
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA can do a work in 36 days and B in 12 days. If they work on it together, then in how many days will they be able to do the work?
View SolutionA takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View SolutionA can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?
View SolutionA and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
View Solution