Trade on the New York Stock Exchange was (506)_______ to a standstill on an autumn day (507)_________ 1994. The culprit for the outage (508)_________ a squirrel that had chewed through a power line near the computer centre of the (509)________ in Trumbull, Connecticut. The shutdown (510)_________ lasted for half an hour, resulted in the NYSE operating system at 85% capacity.
worked
worked
taken
brought
The correct Answer is:D
(d) Brought - to cause somebody/something to be in a certain place or condition
Taken- to carry or move somebody/something, to go with somebody from one place to another
Happened- to take place, usually without being planned first(of an event or situation)
Worked-to make yourself/somebody work, especially very hard So, option (a) is the most suitable answer for the blank.
Similar Questions
In the following passage some words have been deleted. Fill in the blanks with the help of the alternatives given. Trade on the New York Stock Exchange was (506)_______ to a standstill on an autumn day (507)_________ 1994. The culprit for the outage (508)_________ a squirrel that had chewed through a power line near the computer centre of the (509)________ in Trumbull, Connecticut. The shutdown (510)_________ lasted for half an hour, resulted in the NYSE operating system at 85% capacity. Select the most appropriate option for blank no 509. (a) town (b) store (c) exchange (d) bank
View SolutionIn the following passage some words have been deleted. Fill in the blank with the help of the alternatives given. Select the most appropriate option for each blank.
Trade on the New York Stock Exchange was (1) ______ to a standstill on an autumn day (2) ______ 1994. The culprit for the outage (3) ______ a squirrel that had chewed through a power line near the computer cen- tre of the (4) ______ in Trumbull, Connecti- cut. The shutdown (5) ______ lasted for half-an- hour, resulted in the NYSE operating at 85 percent capacity.
SubQuestion No: 24
Select the most appropriate option for blank No. 5.
View Solution
Knowledge Check
In the following passage some words have been deleted. Fill in the blank with the help of the alternatives given. Select the most appropriate option for each blank.
Trade on the New York Stock Exchange was (1) ______ to a standstill on an autumn day (2) ______ 1994. The culprit for the outage (3) ______ a squirrel that had chewed through a power line near the computer cen- tre of the (4) ______ in Trumbull, Connecti- cut. The shutdown (5) ______ lasted for half-an- hour, resulted in the NYSE operating at 85 percent capacity.
Sub Question No : 20 .
Select the most appropriate option for blanks No : 1.AworkedBhappenedCtakenDbroughtIn the following passage some words have been deleted. Fill in the blank with the help of the alternatives given. Select the most appropriate option for each blank.
Trade on the New York Stock Exchange was (1) ______ to a standstill on an autumn day (2) ______ 1994. The culprit for the outage (3) ______ a squirrel that had chewed through a power line near the computer cen- tre of the (4) ______ in Trumbull, Connecti- cut. The shutdown (5) ______ lasted for half-an- hour, resulted in the NYSE operating at 85 percent capacity.
SubQuestion No: 21
Select the most appropriate option for blank No. 2.AinBbyCatDonIn the following passage some words have been deleted. Fill in the blanks with the help of the alternatives given. Trade on the New York Stock Exchange was (506)_______ to a standstill on an autumn day (507)_________ 1994. The culprit for the outage (508)_________ a squirrel that had chewed through a power line near the computer centre of the (509)________ in Trumbull, Connecticut. The shutdown (510)_________ lasted for half an hour, resulted in the NYSE operating system at 85% capacity. Select the most appropriate option for blank No. 3. (a) is (b) were (c) was (d) has
AisBwereCwasDhas