Doubtnut Promotions Sticky

A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working , alone, finish the whole work? 2.days, 7.5 days b. 5 days, 8.5 days c. 5 days, 15 days d. none of these

A

5 days, 8.5 days

B

2.5 days, 7.5 days

C

5 days, 15 days

D

3 days, 15 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working , alone, finish the whole work? 2. d a y s ,\ 7. 5\ d a y s b. 5\ d a y s ,\ 8. 5\ d a y s c. 5\ d a y s ,\ 15\ d a y s d. none of these by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Arjun started a task and left it after working for 2 days. Then, Bharath was called and he completed the task in 9 days. If Arjun alone had worked for 3 days, Bharath alone would have finished the remaining work in 6 days. In how many days can Arjun alone complete the task?

    A8 days
    B12 days
    C5 days
    D10 days
  • Question 2 - Select One

    A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?

    A60
    B50
    C40
    D30
  • Question 3 - Select One

    Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

    A20 days
    B24 days
    C18 days
    D22 days