Doubtnut Promotions Sticky

It takes 8,12 and 16 days for X, Y and Z respectively to complete a work. How many days will it take to complete the work if X works on it for 2 days, and then Y works on it for until 25% of the work is left for Z to do, and then Z complete the work?

A

10 days

B

12 days

C

8 days

D

14 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step-by-step, we will break it down into manageable parts.

Step 1: Determine the work done by X, Y, and Z in one day.
- X completes the work in 8 days, so the work done by X in one day is:
Work done by X in 1 day=18

- Y completes the work in 12 days, so the work done by Y in one day is:
Work done by Y in 1 day=112

- Z completes the work in 16 days, so the work done by Z in one day is:
Work done by Z in 1 day=116

Step 2: Calculate the work done by X in 2 days.
- In 2 days, X will complete:
Work done by X in 2 days=2×18=28=14

Step 3: Calculate the remaining work after X works for 2 days.
- The total work is considered as 1 (or 100%). After X completes 14 of the work, the remaining work is:
Remaining work=114=34

Step 4: Determine how much work Y needs to do before leaving 25% of the work for Z.
- 25% of the total work is:
25%=25100=14
- Therefore, Y will work until 14 of the work is left, which means Y will complete:
Work done by Y=3414=24=12

Step 5: Calculate how many days Y takes to complete 12 of the work.
- Since Y does 112 of the work in one day, the number of days Y needs to complete 12 of the work is:
Days taken by Y=12112=12×121=6 days

Step 6: Calculate the work remaining for Z.
- After Y completes 12 of the work, the remaining work for Z is:
Remaining work for Z=14 (as calculated earlier)

Step 7: Calculate how many days Z takes to complete the remaining work.
- Since Z completes 116 of the work in one day, the number of days Z needs to complete 14 of the work is:
Days taken by Z=14116=14×161=4 days

Step 8: Calculate the total time taken to complete the work.
- The total time taken is the sum of the days worked by X, Y, and Z:
Total days=2 (days by X)+6 (days by Y)+4 (days by Z)=12 days

Final Answer:
The total number of days required to complete the work is 12 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days
  • Question 2 - Select One

    A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days
  • Question 3 - Select One

    If A, B and C can respectively complete a piece of work in 20, 24 and 36 days respectively, how many days will they take to complete the work, if they work together?

    A81643
    B614
    C914
    D71920