A man completes 5/8 of a job in 10 days. At this rate, how many more days will it take him to finish the job?

A

5

B

6

C

7

D

712

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow the reasoning outlined in the video transcript.

Step 1: Understand the total work done
The man completes 58 of a job in 10 days. We can assume the total work to be 1 unit.

Step 2: Calculate the time taken to complete the whole job
If 58 of the job takes 10 days, we can find out how long it would take to complete the entire job (1 unit) using the formula:
Total time for 1 unit=Time taken for 58 of the job×1 unit58 unit
This simplifies to:
Total time for 1 unit=10 days×85=16 days

Step 3: Determine the remaining work
The remaining work to be done is:
Remaining work=158=38 of the job

Step 4: Calculate the time to finish the remaining work
Now, we need to find out how many days it will take to complete the remaining 38 of the job. Since we know that the entire job takes 16 days, we can set up the equation:
Time for 38 of the job=38×16 days
Calculating this gives:
Time for 38 of the job=3×168=488=6 days

Conclusion
Thus, the man will take 6 more days to finish the job.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A man completes 49 of a job in 12 days. At this rate, how many more days will it take him to finish the job ?

    A15
    B10
    C9
    D712
  • Shantanu completes 5/8 of a job in 20 days. At this rate, how many more days will he take to finish the job ?

    A6 days
    B18 days
    C5 days
    D12 days
  • A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?

    A1014
    B1134
    C1114
    D1113