Doubtnut Promotions Sticky

Sixty-four men working 8 h a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 days. How many hours per day should they need to work in order to achieve the target?

A

11

B

12

C

13

D

15

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break it down:

Step 1: Calculate the total work
Assume the total work to be 100 units.

Step 2: Calculate the work done in 5 days
The total number of men is 64, and they work 8 hours a day for 5 days.
- Work done in 5 days = Number of men × Hours per day × Days worked
- Work done = 64 men × 8 hours/day × 5 days = 2560 man-hours

Step 3: Calculate the percentage of work completed
According to the problem, they completed 40% of the work in 5 days.
- Work completed = 40% of 100 = 40 units

Step 4: Calculate the work rate
Since they completed 40 units in 2560 man-hours, we can find the work rate.
- Work rate = Total work completed / Total man-hours = 40 units / 2560 man-hours = 0.015625 units/man-hour

Step 5: Calculate the remaining work
The remaining work is:
- Remaining work = Total work - Work completed = 100 - 40 = 60 units

Step 6: Calculate the total man-hours needed to complete the remaining work
To find out how many man-hours are needed to complete the remaining 60 units:
- Total man-hours needed = Remaining work / Work rate = 60 units / 0.015625 units/man-hour = 3840 man-hours

Step 7: Calculate the daily work hours required to finish the remaining work in 4 days
Now, they want to complete the remaining work in 4 days. Let H be the number of hours they need to work per day.
- Total man-hours = Number of men × Hours per day × Days = 64 men × H hours/day × 4 days
- Setting this equal to the total man-hours needed:
64×H×4=3840

Step 8: Solve for H
256H=3840
H=3840256=15

Conclusion
The number of hours per day they need to work to complete the remaining work in 4 days is 15 hours.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?

    A2012 days
    B2035 days
    C21days
    D2047 days
  • Question 2 - Select One

    Working 10 hours a day, Aman can complete a piece of work in 18 days. How many hours a day should he work so as to finish the work in 15 days ?

    A10
    B12
    C16
    D18
  • Question 3 - Select One

    Working 6 hours a day, Raman can complete a piece of work in 24 days. How many hours a day should he work so as to finish the work in 18 days?

    A8
    B10
    C12
    D16