Sixty-four men working 8 h a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 days. How many hours per day should they need to work in order to achieve the target?
11
12
13
15
The correct Answer is:D
To solve the problem step by step, let's break it down:
Step 1: Calculate the total work
Assume the total work to be 100 units.
Step 2: Calculate the work done in 5 days
The total number of men is 64, and they work 8 hours a day for 5 days.
- Work done in 5 days = Number of men × Hours per day × Days worked
- Work done = 64 men × 8 hours/day × 5 days = 2560 man-hours
Step 3: Calculate the percentage of work completed
According to the problem, they completed 40% of the work in 5 days.
- Work completed = 40% of 100 = 40 units
Step 4: Calculate the work rate
Since they completed 40 units in 2560 man-hours, we can find the work rate.
- Work rate = Total work completed / Total man-hours = 40 units / 2560 man-hours = 0.015625 units/man-hour
Step 5: Calculate the remaining work
The remaining work is:
- Remaining work = Total work - Work completed = 100 - 40 = 60 units
Step 6: Calculate the total man-hours needed to complete the remaining work
To find out how many man-hours are needed to complete the remaining 60 units:
- Total man-hours needed = Remaining work / Work rate = 60 units / 0.015625 units/man-hour = 3840 man-hours
Step 7: Calculate the daily work hours required to finish the remaining work in 4 days
Now, they want to complete the remaining work in 4 days. Let H be the number of hours they need to work per day.
- Total man-hours = Number of men × Hours per day × Days = 64 men × H hours/day × 4 days
- Setting this equal to the total man-hours needed:
64×H×4=3840
Step 8: Solve for H
256H=3840
H=3840256=15
Conclusion
The number of hours per day they need to work to complete the remaining work in 4 days is 15 hours.
---
Assume the total work to be 100 units.
The total number of men is 64, and they work 8 hours a day for 5 days.
- Work done in 5 days = Number of men × Hours per day × Days worked
- Work done = 64 men × 8 hours/day × 5 days = 2560 man-hours
According to the problem, they completed 40% of the work in 5 days.
- Work completed = 40% of 100 = 40 units
Since they completed 40 units in 2560 man-hours, we can find the work rate.
- Work rate = Total work completed / Total man-hours = 40 units / 2560 man-hours = 0.015625 units/man-hour
The remaining work is:
- Remaining work = Total work - Work completed = 100 - 40 = 60 units
To find out how many man-hours are needed to complete the remaining 60 units:
- Total man-hours needed = Remaining work / Work rate = 60 units / 0.015625 units/man-hour = 3840 man-hours
Now, they want to complete the remaining work in 4 days. Let H be the number of hours they need to work per day.
- Total man-hours = Number of men × Hours per day × Days = 64 men × H hours/day × 4 days
- Setting this equal to the total man-hours needed:
64×H×4=3840
256H=3840
H=3840256=15
The number of hours per day they need to work to complete the remaining work in 4 days is 15 hours.
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself
15 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)
37 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
On working 10 hourse a day, 15 men can complete a piece of work in 20 days. In how many days can 30 men complete if they work 5 hours per day?
View SolutionWorking 15 hours a day, Goldy can complete a piece of work in 24 days. How many hours a day he should work so as to finish the work in 18 days?
View Solution
Knowledge Check
8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
A2012 daysB2035 daysC21daysD2047 daysWorking 10 hours a day, Aman can complete a piece of work in 18 days. How many hours a day should he work so as to finish the work in 15 days ?
A10B12C16D18Working 6 hours a day, Raman can complete a piece of work in 24 days. How many hours a day should he work so as to finish the work in 18 days?
A8B10C12D16
Working 15 hours a day, Goldy can complete a piece of work in 24 days. How many hours a day he should work so as to finish the work in 18 days?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution16 persons working 6 hours a day can complete a work in 10 days. In how many days 24 persons working 8 hours a day will complete 80% of that work?
एक दिन में 6 घंटे कार्य करके 16 व्यक्ति किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | एक दिन में 8 घंटे कार्य करके 24 व्यक्ति इस कार्य का 80% भाग कितने दिनों में समाप्त कर सकते हैं ?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution