8 men and 14 women are working together in a field. After working for 3 days, 5 men and 8 women leave the work. How many more days will be required to complete the work?
I. 19 men and 12 women together can complete the work in 18 days.
II. 16 men complete two-third of the work in 16 days
III. In a day, the work done by three men is equal to the work done by four women.

A

I only

B

II only

C

III only

D

I or II or III

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step-by-step, we need to determine how many more days will be required to complete the work after some workers leave.

Step 1: Understand the initial work done
We have:
- 8 men and 14 women working together for 3 days.

Let:
- The work done by 1 man in 1 day = x
- The work done by 1 woman in 1 day = y

The total work done by 8 men and 14 women in 3 days is:
Work done in 3 days=3×(8x+14y)=24x+42y

Step 2: Calculate remaining workers after 3 days
After 3 days, 5 men and 8 women leave:
- Remaining men = 8 - 5 = 3
- Remaining women = 14 - 8 = 6

Step 3: Set up the equation for remaining work
Let D be the number of days required to complete the remaining work. The work done by the remaining workers in D days is:
Remaining work=D×(3x+6y)

Step 4: Total work equation
The total work done can be expressed as:
Total work=Work done in 3 days+Remaining work
This gives us:
1=24x+42y+D(3x+6y)

Step 5: Analyze the statements
We have three statements that can help us find the values of x and y.

Statement I: 19 men and 12 women can complete the work in 18 days.
Work=19x+12y in 1 day18(19x+12y)=1

Statement II: 16 men complete two-thirds of the work in 16 days.
Work=16x in 1 day16(16x)=2316x=248x=1384

Statement III: The work done by 3 men is equal to the work done by 4 women.
3x=4yy=34x

Step 6: Solve the equations
Using Statement II, we can find x and substitute it into Statement III to find y:
- From Statement II, we have x=1384.
- Substitute x into Statement III to find y:
y=34×1384=31536=1512

Step 7: Substitute values back into the total work equation
Now substituting x and y back into the total work equation:
1=24(1384)+42(1512)+D(3(1384)+6(1512))

Step 8: Calculate the remaining work and solve for D
Calculate the left side:
1=24384+42512+D(3384+6512)
Now, simplify and solve for D.

Final Calculation
After calculating the fractions and simplifying, we find the value of D, which represents the number of additional days needed to complete the work.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • In how many days can 4 women complete a work?
    I. 4 men and 4 women can complete the same work in 12 days.
    II. 10 women can complete the same work in 16 days

    AIf statement I alone is sufficient but statement II alone is not sufficient.
    BIf statement Il alone is sufficient but statement I alone is not sufficient.
    CIf each statement alone (either I or II) is sufficient.
    DIf statement and Il together are not sufficient
  • Ten men or twelve women can finish the same work in 10 days. If 5 men and 2 women undertake the work together, how many days will they take to complete the work?
    दस पुरुष या बारह महिलाएं एक कार्य को 10 दिनों में पूरा कर सकती हैं | यदि 5 पुरुष तथा 2 महिलाओं ने उस कार्य को शुरू किया, तो कार्य पूरा करने में उन्हें कितने दिन लगेंगे ?

    A20
    B15
    C40
    D60
  • 15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32