If 10 masons working 7 h daily can build 28 water tanks in 16 days, then how many days will 12 masons working 6 h daily take to build 36 water tanks?
20
21
22
19
To solve the problem, we will first determine the total work done in terms of mason-hours for the first scenario, and then use that information to find out how many days it will take for the second scenario.
Step 1: Calculate the total work done in mason-hours for the first scenario.
We know:
- Number of masons = 10
- Hours worked daily = 7
- Number of days = 16
- Number of water tanks built = 28
Total work done (in mason-hours) can be calculated as follows:
Total Work=Number of Masons×Hours per Day×Number of Days
Substituting the values:
Total Work=10×7×16=1120 mason-hours
Step 2: Calculate the work done per water tank.
Now, we need to find out how much work is required to build one water tank:
Work per Water Tank=Total WorkNumber of Water Tanks=1120 mason-hours28=40 mason-hours per tank
Step 3: Calculate the total work required for the second scenario.
Now, we need to find out how much work is required to build 36 water tanks:
Total Work for 36 Tanks=Work per Water Tank×Number of Tanks=40×36=1440 mason-hours
Step 4: Calculate the total work done by 12 masons working 6 hours daily.
Now we will calculate how many days it will take for 12 masons working 6 hours daily to complete 1440 mason-hours of work.
Let D be the number of days required. The total work done by 12 masons in D days is:
Total Work=Number of Masons×Hours per Day×D
Substituting the values:
1440=12×6×D
This simplifies to:
1440=72D
Step 5: Solve for D.
Now, we can solve for D:
D=144072=20
Thus, it will take 12 masons working 6 hours daily a total of 20 days to build 36 water tanks.
Final Answer:
20 days
---
- Number of masons = 10
- Hours worked daily = 7
- Number of days = 16
- Number of water tanks built = 28
20 days
Similar Questions
Knowledge Check
- Question 1 - Select One
10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
AA)40 daysBB)60 daysCC)50 daysDD)30 days - Question 2 - Select One
15 labors make a water tank in 12 days, then in how many days will 20 labors make the tank ?
A16B10C8D9 - Question 3 - Select One
If 30 men working 9 h per day can reap a field in 16 days, in how many days, will 36 men reap the field working 8 h per day ?
A15B25C18D10
16 persons working 6 hours a day can complete a work in 10 days. In how many days 24 persons working 8 hours a day will complete 80% of that work?
एक दिन में 6 घंटे कार्य करके 16 व्यक्ति किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | एक दिन में 8 घंटे कार्य करके 24 व्यक्ति इस कार्य का 80% भाग कितने दिनों में समाप्त कर सकते हैं ?View SolutionTwelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?
View SolutionTwelve men, working at 8h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6h a day can do the same work?
View SolutionIf 24 workers can build a wall in 15 days, how many days will 8 workers take to build a similar wall?
View SolutionSixteen men, working at 6 h a day, can do a piece of work in 15 days. In how many days can 18 men working at 10 h a day do the same work?
View Solution