Assume that the moon takes exactly 30 days to complete the cycle and also assume that it rises in the east exactly at 6 : 48 . on the first day . On the fourth day, at what time will it rise /
A
8:24p.m
B
9:12p.m
C
10.00p.m
D
11:48p.m
Text Solution
The correct Answer is:C
Edit Assume that the moon takes exactly 30 days to complete the cycle and also assume that it rises in the east exactly at 6 : 48 . on the first day . On the fourth day, at what time will it rise 10 . 00 p . m
|
Updated on:21/07/2023
Similar Questions
Knowledge Check
- Question 1 - Select One
A alone takes 4 more days to complete a work, in that time A and B can complete it together and B alone takes 16 more days to complete the same. In how many days they will do it together?
A1. 6B2. 8C3. 12D4. 10 - Question 2 - Select One
Which one of the following is one of the two days when the sun rises exactly in the east ?
A14th januaryB21st MarchC21st JuneD23nd December - Question 3 - Select One
A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
A17B19C19.5D21
If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionA is twice as good workman as B.A takes 6 days the complete a work. In what time can B complete the work?
View SolutionA is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
View SolutionFifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.
View Solution