The efficiency of work of P and Q are in the ratio 5 : 7. What will be the ratio of number of days taken by them to finish the work?
A. 7:5
B. 3:4
C. 4:3
D. 5:7
A
D
B
C
The correct Answer is:A
To solve the problem, we need to find the ratio of the number of days taken by P and Q to finish the work, given that their efficiencies are in the ratio of 5:7.
1. Understand the Relationship Between Efficiency and Time:
- Efficiency and time taken to complete a work are inversely proportional. This means that if one person is more efficient, they will take less time to complete the work.
2. Set Up the Efficiency Ratios:
- Let the efficiency of P be 5 units of work per day and the efficiency of Q be 7 units of work per day.
3. Calculate the Time Taken:
- If P can do 5 units of work in one day, the number of days P will take to finish the work can be represented as Time taken by P=1Efficiency of P=15.
- Similarly, for Q, the number of days taken will be Time taken by Q=1Efficiency of Q=17.
4. Find the Ratio of Time Taken:
- The ratio of time taken by P to time taken by Q is given by:
Ratio of time taken=Time taken by PTime taken by Q=1/51/7=75
5. Express the Ratio:
- Therefore, the ratio of the number of days taken by P and Q to finish the work is 7:5.
6. Select the Correct Option:
- From the options provided, the correct answer is A. 7:5.
- Efficiency and time taken to complete a work are inversely proportional. This means that if one person is more efficient, they will take less time to complete the work.
- Let the efficiency of P be 5 units of work per day and the efficiency of Q be 7 units of work per day.
- If P can do 5 units of work in one day, the number of days P will take to finish the work can be represented as Time taken by P=1Efficiency of P=15.
- Similarly, for Q, the number of days taken will be Time taken by Q=1Efficiency of Q=17.
- The ratio of time taken by P to time taken by Q is given by:
Ratio of time taken=Time taken by PTime taken by Q=1/51/7=75
- Therefore, the ratio of the number of days taken by P and Q to finish the work is 7:5.
- From the options provided, the correct answer is A. 7:5.
Similar Questions
Knowledge Check
- Question 1 - Select One
The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio
A3:4B9:16C4:3DNone of these - Question 2 - Select One
The rates of working of A and B are In the ratio of 2:3. The number of days taken by each of them to finish the work is in the ratio:
A2:3B4:9C3:2D9:4 - Question 3 - Select One
B is thrice as efficient as A and C is 0.75 times as efficient as A. What is the ratio of number of days taken by A, B and C when they work individually?
A. 4:1:3
B. 3:1:4
C. 2:3:1
D. 5:1:2ACBACDDB
The ages of A and B are in the ratio 6:5 and the sum of their ages is 44 years. What will be the ratio of their ages after 8 years? a. 7:6 b. 8:7 c. 9:8 d. 3:4
View SolutionA is thrice efficient as B and C is twice as efficient as B. What is the ratio of number of days taken by A, B and C, when the work individually?
View SolutionP is twice as good as Q and together they finish a piece of work in 36 days. The number of days taken by P alone to finish the work?
View Solution2 men or 5 women or 7 boys can finish a work in 469 days. then the number of days taken by 7 men, 5 women and 2 boys to finish the work is :
View Solution2 men or 5 women or 7 boys can finish a work in 469 days. then the number of days taken by 7 men, 5 women and 2 boys to finish the work is :
View Solution