Doubtnut Promotions Sticky

12 men and 16 women together can complete a work in 4 days . It takes 80 days for one man alone to complete the same work , then how many days would be required for one woman alone to complete the same work ?

A

160

B

150

C

130

D

175

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, let's break it down:

Step 1: Understand the Work Done by Men and Women
We know that 12 men and 16 women can complete the work in 4 days.

Step 2: Calculate Total Work in Man-Days
First, we need to convert the work done into man-days. Since it takes 80 days for one man to complete the work alone, the total work can be expressed in man-days as:
Total Work=1 man×80 days=80 man-days

Step 3: Work Done by 12 Men in 4 Days
Now, let’s find out how much work 12 men can do in 4 days:
Work done by 12 men in 4 days=12 men×4 days=48 man-days

Step 4: Work Done by 16 Women in 4 Days
Let’s denote the work done by one woman in one day as W. Therefore, the work done by 16 women in 4 days is:
Work done by 16 women in 4 days=16 women×4 days=64W woman-days

Step 5: Total Work Equation
According to the problem, the total work done by both men and women together in 4 days is equal to the total work in man-days:
48 man-days+64W woman-days=80 man-days

Step 6: Solve for Woman's Work
Now, we can solve for W:
64W=8048
64W=32
W=3264=12 man-days

Step 7: Calculate Days Required for One Woman
If one woman does 12 of a man-day of work in one day, then the number of days required for one woman to complete the entire work (80 man-days) is:
Days required for one woman=80 man-days12 man-days per day=80×2=160 days

Final Answer
Thus, one woman alone would require 160 days to complete the same work.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    16 men and 12 women together complete a work in 20 days. If 18 women complete the same work in 40 days. Then how many days will be taken by 12 men and 27 women together to complete the same work ?

    A18 days
    B15 days
    C14 days
    D16 days
  • Question 2 - Select One

    P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

    A48 days
    B42 days
    C45 days
    D51 days
  • Question 3 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days