Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?
3/5
1/3
1/2
2/5
The correct Answer is:D
To solve the problem step by step, we need to determine how much work Vikram and Vivek have completed together in the 20 days they worked.
Step 1: Determine the work rate of Vikram and Vivek together.
Since Vikram and Vivek can finish the work in 50 days, we can say that their combined work rate is:
Work Rate=1 (complete work)50 days=150 work/day
Step 2: Calculate the total work done in 20 days.
Now, if they worked together for 20 days, the amount of work they completed in that time can be calculated as:
Work Done=Work Rate×Number of Days Worked=150×20
Step 3: Perform the multiplication.
Calculating this gives:
Work Done=2050=25
Step 4: Conclusion
Thus, the total work done by Vikram and Vivek together in 20 days is 25 of the entire work.
Final Answer:
The amount of work done by them is 25.
---
Since Vikram and Vivek can finish the work in 50 days, we can say that their combined work rate is:
Work Rate=1 (complete work)50 days=150 work/day
Now, if they worked together for 20 days, the amount of work they completed in that time can be calculated as:
Work Done=Work Rate×Number of Days Worked=150×20
Calculating this gives:
Work Done=2050=25
Thus, the total work done by Vikram and Vivek together in 20 days is 25 of the entire work.
The amount of work done by them is 25.
Similar Questions
A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ? 40 b. 50 c. 54 d. 60
View SolutionA, B and C working together can finish certain piece of work in 28 days. They work together for 18 days, then B left. If rest work done by A and C in 25 days. Work done by A in 2 days is equal to work done by C in 3 days, then find in how many days A, B and C working alone will finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
S and T can finish a work in 50 days. They worked together for 20 days and then left . How much of the work is left
A3/5B1/3C1/2D2/5 - Question 2 - Select One
A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?
A50 daysB60 daysC48 daysD54 days - Question 3 - Select One
A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…
A48 daysB50 daysC54 daysD60 days
A, B and C working together can finish a piece of work in 32 days. They started working together and worked for 20 days then A left the work. Rest work done by B and C in 20 days. In how many days A working alone will finish the work?
View SolutionP and Q can finish a work in 30 days. They worked at it for 10 days and then Q left. The remaining work is done byPalone in 20 more days. How long willPtake to finish the work alone?
View SolutionA and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
View SolutionA can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?
View SolutionA can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?
View Solution