A can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?
12
16
18
15
The correct Answer is:C
To solve the problem, we will follow these steps:
Step 1: Determine A's work rate
A can complete the work in 24 days. Therefore, A's work rate is:
Work rate of A=1 work24 days=124 work per day
Step 2: Calculate B's efficiency
B is 50% more efficient than A. To find B's work rate, we first calculate 50% of A's efficiency:
50% of A's work rate=0.5×124=148
Now, we add this to A's work rate to find B's work rate:
Work rate of B=Work rate of A+50% of A's work rate=124+148
Step 3: Find a common denominator
To add the fractions, we need a common denominator. The least common multiple of 24 and 48 is 48. We convert 124 to have a denominator of 48:
124=248
Now we can add the two fractions:
Work rate of B=248+148=348=116 work per day
Step 4: Calculate the time taken by B to complete the work
To find out how many days B takes to complete the work, we take the reciprocal of B's work rate:
Days taken by B=1 workWork rate of B=1116=16 days
Final Answer
B can complete the work in 16 days.
---
A can complete the work in 24 days. Therefore, A's work rate is:
Work rate of A=1 work24 days=124 work per day
B is 50% more efficient than A. To find B's work rate, we first calculate 50% of A's efficiency:
50% of A's work rate=0.5×124=148
Now, we add this to A's work rate to find B's work rate:
Work rate of B=Work rate of A+50% of A's work rate=124+148
To add the fractions, we need a common denominator. The least common multiple of 24 and 48 is 48. We convert 124 to have a denominator of 48:
124=248
Now we can add the two fractions:
Work rate of B=248+148=348=116 work per day
To find out how many days B takes to complete the work, we take the reciprocal of B's work rate:
Days taken by B=1 workWork rate of B=1116=16 days
B can complete the work in 16 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?
A24B32C18D15 - Question 2 - Select One
P can do a piece of work in 36 days. If Q is 50% more efficient than P, then in how many days can Q do the same work?
A18B24C12D21 - Question 3 - Select One
A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in
A10daysB712 daysC12daysD1012 days
A can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?
View SolutionA can do a certain job in 12 days. B in 60% more efficient than A. What is the number of days it takes B to do the same piece of work ?
View SolutionA can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is :
View SolutionA can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is :
View SolutionP can do a work in 9 days and Q is 50% more efficient than P. In how many days can Q do it alone ?
View Solution