16 workers working 8 hours per day can demolish a building in 32 days. In how many days 24 workers working 12 hours per day can demolish the same building?
1283 days
563 days
1289 days
569 days
The correct Answer is:C
To solve the problem, we can use the concept of work done, which can be expressed in terms of the number of workers, the number of days they work, and the number of hours they work each day. The relationship can be summarized with the formula:
M×D×H=W
Where:
- M = Number of workers
- D = Number of days
- H = Number of hours worked per day
- W = Total work done (which we can consider as 1 for this problem since we are looking for the same building to be demolished)
1. Calculate the total work done by the first group of workers:
- Number of workers (M1) = 16
- Hours per day (H1) = 8
- Days (D1) = 32
Using the formula:
W=M1×D1×H1=16×32×8
2. Calculate the total work done:
W=16×32×8=4096 worker-hours
3. Set up the equation for the second group of workers:
- Number of workers (M2) = 24
- Hours per day (H2) = 12
- Days (D2) = ?
Using the same formula:
W=M2×D2×H2
Substituting the known values:
4096=24×D2×12
4. Solve for D2:
4096=288×D2
D2=4096288
5. Calculate D2:
D2=4096÷16288÷16=25618=1289
Conclusion:
Thus, the number of days required for 24 workers working 12 hours per day to demolish the same building is 1289 days.
- M = Number of workers
- D = Number of days
- H = Number of hours worked per day
- W = Total work done (which we can consider as 1 for this problem since we are looking for the same building to be demolished)
- Number of workers (M1) = 16
- Hours per day (H1) = 8
- Days (D1) = 32
W=M1×D1×H1=16×32×8
W=16×32×8=4096 worker-hours
- Number of workers (M2) = 24
- Hours per day (H2) = 12
- Days (D2) = ?
W=M2×D2×H2
Substituting the known values:
4096=24×D2×12
4096=288×D2
D2=4096288
D2=4096÷16288÷16=25618=1289
Thus, the number of days required for 24 workers working 12 hours per day to demolish the same building is 1289 days.
Similar Questions
Knowledge Check
18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field?
A9B10C6D810 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
AA)40 daysBB)60 daysCC)50 daysDD)30 days16 persons working 6 hours a day can complete a work in 10 days. In how many days 24 persons working 8 hours a day will complete 80% of that work?
एक दिन में 6 घंटे कार्य करके 16 व्यक्ति किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | एक दिन में 8 घंटे कार्य करके 24 व्यक्ति इस कार्य का 80% भाग कितने दिनों में समाप्त कर सकते हैं ?A3B6C4D8
4 men, each working 6 hours per day can build a wall in 9 days. How long will 6 men, each working 3 hours per day take to finish the same work?
View SolutionIf 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?
View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution